Thermosiphon meeting

→ Europe/Zurich
629-R-013 (CERN)

629-R-013

CERN

Michele Battistin (CERN)
    • 10:00 → 10:10
      Action List 10m
      Cabling: Florian will do a tour with INEO to identify the missing connection. Florian. Pneumatics: Everything is connected on the roof, but degassing and Swagelock valve. Balcony: pipes close to items, ready to be connected. all the pneumatics connection are missing: Cyril is taking over Mapping of the pneumatic valves to be finished Mapping of the pneumatic actuators Re-do the piping distribution on the valve side. Pierre + Florian A TT is missing on the C6F14 circuit close to the condenser: Pierre has dismounted one of the two connections and Sylvain will install a "doit de gant" there. By-pass of the C6F14 to clean the line before connection the condenser. It shall be designed (Pierre?) and realised (Sylvain?). Do it on the DN25. H2O circuit lagging. Tchuflan start next week. VIC Friday 23rd. Execute small insulation on the by-pass (between lamination valve and HEX). DONE Finish the insulation on the roof Ouvaroff has worked yesterday… Put the leak check from scanned on EDMS (Pierre). Install actuator DN200 over the balcony unit (50 kg). We need to install a hook on the roof. Transport is studying the problem. Modify the actuator of the valve PCV2102B from NC to NO. Cyril asap. Check connections on the H2O skid. Daniel said that many sensors are not connected. Michele to check with Mus. Etiquettes: Pierre is filling the Infor database on excel format Once done we can produce the etiquette. Olivier will buy the etiquette printer. The chiller equipment shall be entered too Etiquettes for external installation to be done. Hard etiquettes shall be produced. Fix the pipe passages on the walls on different locations: Michele will send mail to Eliseo. Modify and re-install the stairs to go around the cryogenic pipe close to the C6F14 pumping station. Cyril, on going. Protection over the hole for the passage of the pipes from the chiller zone to the technical gallery, Cyril + Juri and Michail. Ask Wieslaw confirmation that we can put power on all the cupboards. Olivier confirmed that Bruno S.Suplice confirmed. Wislaw we can ask EL to do whenever we want. Dismounting of the scaffolding next week. PV1103: liquid by-pass: waiting for the valve, two DN20 PN40 flanges to be ordered. Pierre. Then Sylvain to weld. Check the procedure to fill-empty the C6F14 line to connect it to the condenser after cleaning. Install a red telephone on the roof. Ask Eliseo concerning the roof on the condenser Protect the cable tray on the roof (Cyril + Juri and Michail) Install the dryers on the C6F14 before filling. I/O List check between Florian and Lukasz.
    • 10:10 → 10:50
      Actions List Review 40m
      Speaker: Michele Battistin (CERN)
    • 10:50 → 11:00
      Any Other Business 10m
      Speakers: Claudio Bortolin (Universita e INFN (IT)), Cyril Degeorge (Indiana University (US)), Daniel Lefils (CERN), Florian Corbaz (CERN), Gregory Hallewell (Centre National de la Recherche Scientifique (FR)), Jan Godlewski (CERN), Lukasz Zwalinski (CERN), Olivier Crespo-Lopez (CERN)