Cabling: visit this morning with Florian
Water circuit: no GS on valve GS1531 and the GS on the HV1530 – Pierre is taking over
Condenser: one TT on the bottom of the condenser + the TT of Sylvain on the C6F14 installed – they have to be cabled - Florian
Swagelock by-pass valve on the liquid line PV1103 is missing (to be cabled) - Sylvain is finishing it – Cyrill will install it.
Sonar part: PV1221 missing, PV1222 missing, PT1202 missing, ST1201 + ST1202 are missing, vacuum pump is missing. Michele to write to Greg.
Brine: FT1350 to be cabled.
By-pass: actuator of valve PV2201 switch to be cabled.
On all the external cabling all the "penduilles" shall be black and the white ones shall be taken out (the sun will destroy them) (Cyril = Juri and Michail)
Florian: INEO will cable everything when all will be installed.
Check the signal of the scale of the condenser.
One power cable is missing: Mito shall lay it down.
Nacelle interference in SX1. Olivier to discuss with René Necca.
Florian to purchase a new cable.
Pneumatics:
Everything is connected on the roof, but degassing and Swagelock valve which is not installed yet.
All done but:
Cleaning the aorta for the Open Days - Cyril
Balcony: actuator to be installed and connected.
Pneumatic mapping - DONE
Re-install the flange with the new TT on the C6F14 circuit close to the condenser - DONE
By-pass of the C6F14 to clean the line before connection the condenser. Waiting for the filter – supposed to arrive on 23/9. running
Finish the insulation on the roof. All done a part last Swagelock valve + final insulation after C6F16 connection.
Put the leak check document from scanned on EDMS (Pierre).
Install actuator DN200 over the balcony unit (50 kg). Scaffolding on Monday 23/9, installation on Tuesday 24/9.
Chiller: Cyrill to install the CE plates of the heat exchangers and tanks of the chiller.
Etiquettes: Pierre is filling the Infor database on excel format
Claudio to retrieve the information form Stefano Moccia concerning Water circuit
Claudio to recuperate the information for the chiller.
Once done we can produce the etiquette.
Olivier has bought the etiquette printer. Training foreseen in the next weeks.
Etiquettes for external installation to be done. Hard etiquettes shall be produced (Claudio).
Fix the pipe passages on the walls on different locations: Michele sent mail to Eliseo. No answer for the time being.
Modify and re-install the stairs to go around the cryogenic pipes close to the C6F14 pumping station. DONE.
Protection over the hole for the passage of the pipes: ready. DONE.
SH1 Dismounting of the scaffolding: DONE
PV1103: liquid by-pass: Sylvain is finishing now. Cyril will install tomorrow 20/9.
Check the procedure to fill-empty the C6F14 line to connect it to the condenser after cleaning.
Filling at filter level
Emptying from the technical gallery.
Install the dryers and try the filling pump (Pierre + Cyril) after installation of the by pass.
Red telephones (Olivier):
Install a red telephone on the roof
move the red telephone form the balcony moved tomorrow.
Ask Eliseo concerning the roof on the condenser (Michele): before snowing…
Protect the cable tray on the roof Cyril will provide elements to Olivier to call the supplier.
I/O list check between Florian and Lukasz. DONE
Control: answer from J&E Hall received: Michele and Lukasz to call them today or tomorrow.
H2O: PV1501 on-off instead that PCV. The pump is not fixed. We mis two switches.
Electrical cupboard HSE visit certification: Florian has given the document to Anders.
Power on all the cupboards Wieslaw said whenever we want. Waiting for HSE certification.
Problem on the torc on the PV4301: Pierre has added two springs. OK.
Documentation: Ceclia to suggest a folder structure for EDMS.
Claudio to prepare the commissioning forms starting form the commissioning document of Jose.
Brine temperature regulation to be checked… Pierre, Stephane, Olivier, Lukasz, Jan.
Thermosiphon PLC program is ready: under simulator now. Ask for Benjamin presentation.