Conveners
Tuesday morning 2
- Alireza Nassiri (Argonne National Laboratory)
Mark Wissmann
(J)
13/05/2014, 11:00
SPC judgements
Oral presentation
CEBAF (Continuous Electron Beam Accelerator Facility) at Jefferson Lab was initially designed to deliver up to a 4 GeV electron beam simultaneously to three experimental halls. The maximum deliverable energy was raised to 6 GeV and CEBAF ran there until May of 2012 after which CEBAF entered an extensive, upgrade shutdown. After the upgrade, scientists plan to use CEBAF to deliver 11 GeV beam...
Hartmut Büttig
(Helmholtz Zentrum Dresden-Rossendorf)
13/05/2014, 11:30
SPC judgements
Oral presentation
H. Büttig, A. Arnold, A. Büchner, M. Justus, M. Kuntzsch, U. Lehnert, P. Michel, R.Schurig, G. Staats, J.Teichert.
Radiation Source ELBE, Helmholtz Zentrum Dresden- Rossendorf, Germany
Abstract:
In January 2012 the 10 kW klystrons of the CW LINAC ELBE were replaced by pairs of 10kW solid state power amplifiers (SSPA).
The talk gives an overview on the SSPA based ELBE RF system....
Mr
James Rose
(Brookhaven)
13/05/2014, 12:00
SPC judgements
Oral presentation
The NSLS-II has completed early commissioning with the booster synchrotron utilizing a 80 kW IOT transmitter powering a 7-cell “PETRA” like cavity and the storage ring a 300 kW klystron transmitter powering an identical cavity. The 7-cell cavity in the storage ring will be replaced with a “CESR-B” like superconducting cavity during the May 2014 shutdown. Both the klystron and IOT transmitters...