- Event driven by view from operation - invitation to an open discussion
- Scenarios: commissioning to 450 GeV, 2 TeV and 4 .. 6 TeV
- Key dates in preparation for the next sector and outlook to planning
- Discussions on improvements: what can be done in the next 3-4 weeks?
- 2 shifts during 5 days versus 3 shifts during 7 days, , MPP analysis, what can be done in a nightshift – WE? Bottlenecks in manpower
- Organisation: HC coordinator on a weekly basis? For coordination between sectors etc.
- (written) guidelines for operators (coordination tools, conditions for powering)
- Commissioning meetings efficient? How continue activities during meetings?
- Follow-up by mini teams on: Automatic commissioning and controls issues, Tools required to optimize commissioning, Organisation, System upgrades and improvements