September 28, 2015 to October 2, 2015
Lisbon
Europe/Zurich timezone

ATLAS Pixel Detector ROD card from IBL towards Layers 2 and 1

Sep 29, 2015, 9:50 AM
25m
Lisbon

Lisbon

IST (Instituto Superior Técnico ) Alameda Campus Av. Rovisco Pais, 1 1049-001 Lisboa Portugal

Speaker

Alessandro Gabrielli (Universita e INFN, Bologna (IT))

Description

ATLAS Experiment has reworked and upgraded some systems during the 2014-2015 LHC shut down and the Pixel Detector has inserted an additional layer: the Insertable B-Layer. The Readout-Driver card, the Back-of-Crate card, and the S-Link together form the essential frontend data path of the IBL’s off-detector DAQ system. Recent collaboration efforts focused on hardware and firmware and now the work is moving towards the DAQ upgrades of the Layers 2 and 1, leaving the sensors untouched. Time plan is to approach a complete DAQ hardware-software installation by the end of 2015.

Summary

The strategy for Insertable B-Layer (IBL) Readout-Driver (ROD) firmware development was three-fold: keeping as much of the Pixel ROD datapath firmware logic as possible, employing a complete new scheme of steering and calibration firmware and designing the overall system to prepare for a unified code version integrating IBL and Pixel layers. Essential features such as data formatting, frontend-specific error handling, and calibration are added to the ROD data path. An IBL DAQ testbench using realistic frontend chip model was created to serve as an initial framework for full offline electronic system simulation.
In this document, major hardware and firmware achievements concerning the IBL ROD data path implementation, tested in testbench and on ROD prototypes, will be reported.
For ATLAS Pixel Detector Layer 2, which requires 26 additional pairs of Back-of-Crate (BOC) and ROD cards, we have carried out a new production of the IBL cards for further boards. In fact, the IBL boards can easily expand the bandwidth of Pixel Layer 2 as long as we provide dedicated firmware to interface with the present detector and, in particular, with the FEI3 chips instead of the IBL FEI4s. For Layer 2, including the spare cards used also for IBL, 40 RODs have been fabricated in 2014 and are going to be installed in 2015, just after the IBL commissioning. The same approach used for upgrading the Layer 2 will be used to upgrade the 38 ROD cards used in the Pixel Detector Layer 1. This additional production has not yet started and the plan is to have it completed by the end of 2015. Implementation of the new DAQ boards for Layer 1 is instead planned for the shut down of winter 2016.

Primary author

Alessandro Gabrielli (Universita e INFN, Bologna (IT))

Presentation materials