GENERAL SERVICES INSTALLATION: ASSESSMENT OF THE PLANNING AND COORDINATION IN THE FIELD

24 May 2005, 09:50
20m
JURA building (Archamps)

JURA building

Archamps

Site d'Archamps F-74160 Archamps
Presentation LHC Installation, comissioning and operation from CCC session 1

Speaker

Mr S. Grillot (CERN)

Description

The start of the LHC installation in 2002 followed immediately the LEP dismantling. The first phase, i.e. the general services installation which is drawing to a close has involved about ten different trades, distributed in seven Groups all working with different types and sizes of contracts. This task has been planned and coordinated by the Installation Coordination Group of the TS Department. Three years after the start of the works, we aim at making an assessment of the planning and coordination in the field. This paper will present the evolution of the work in this phase and will introduce a critical analysis focusing on scheduling, deadline keeping, coordination, general and particular organization, technical organization, safety, etc.

Authors

Mrs K. Foraz (CERN) Mr S. Grillot (CERN)