EGEE-SA1-SWE Meeting

→ Europe/Zurich
VRVS Virtual Room (http://www.vrvs.org)

VRVS Virtual Room (http://www.vrvs.org)

Pacheco, Andreu
Description
Andreu Pacheco will be substituted by Gonzalo Merino. Andreu will be at CERN from July 19th to August 18th. His phone will be +41 22 767 6063 (32-SA-18).
    • 12:00 → 12:15
      Briefing of activities 15m VRVS

      VRVS

      Speaker: Pacheco, Andreu (IFAE/PIC)
      more information
    • 12:05 → 12:15
      Operational status from sites 10m VRVS

      VRVS

      * From February 1st 2005 all sites must report by mail their operational status each friday if they want Gonzalo Merino to report with accuracy their status to EGEE Operations Meeting * Since the people from CERN is asking the ROCs to write the monday's 11 report following a sort of template, I think it will be useful that the SWE Site Reports that site managers are sending on friday to this list, try to follow a similar template as well. I suggest then that these reports are produced following the template available at: https://services2.pic.org.es/devel/download/txt/SR-SWE-Template.txt * Reports should be sent to: egee.swe.roc.contact@pic.es The reports from SWE are appended to the agenda page of the weekly operation meetings: http://agenda.cern.ch/displayLevel.php?fid=258
      Speaker: Merino, Gonzalo (PIC)
      • CESGA-EGEE 15m
        Hola, El link que has mandado con el template del report parece roto. Aqui va mi report, no hay novedades: --8<-------- Site name: CESGA-EGEE Report period: 11/07/05 to 17/07/05 Operational Issues ================== No major problems this week. -------->8-- Hasta luego -- Javier Fontan - jfontan@cesga.es Supercomputing Center of Galicia Avda. de Vigo s/n. Campus Sur. 15705 - Santiago de Compostela. SPAIN Tlfn.: +34 981569810 Fax: +34 981594616
        Speaker: Fontan, Javier
      • CIEMAT-LCG2 15m
        Weekly Operations Status Report: CIEMAT-LCG2 Reporting Period: 09/07/05 to 15/07/05 Availability of Core Services Hosted in the Site ================================================== There is no core services running at CIEMAT at this moment Non-Functional Time ==================== None Scheduled Down Time =================== * Scheduled Maintenance During the Reporting Period 0 * Scheduled Maintenance During the Next Reporting Period 0 Major Operational Issues Encountered During the Reporting Period ================================================================ During this period we have had 2 unexpected shutdowns in our Computer Center. As we have all our worker nodes in his machine room, we lost Gstat hourly tests on Tuesday afternoon (20:00-22:00). Since this Friday we are supporting biomed VO We are still on LCG-2.4.0 Upgrade to Scientific Linux 3 (or equivalent) ============================================= By when will all service nodes in the Site be upgraded? Completed, now Scientific Linux 3.0.4 By when will the WNs in the Site be upgraded? Completed, now Scientific Linux 3.0.4 Points to Raise at the Operations Meeting ========================================= None
        Speaker: Calonge, Javier
      • CNB-LCG2 15m
        Speaker: No contact person
      • IFCA-LCG2 15m
        Speaker: Cano, Dani
      • IFIC-LCG2 15m
        -- Weekly Operations Status Report: IFIC-LCG2 Reporting Period: 11/07/2005 to 18/07/2005 Availability of Core Services Hosted in the Site RB: lcg2rb.ific.uv.es (public use) [OK] RB: lcg2rb2.ific.uv.es (ATLAS production) [OK] BDII: lcg2bdii.ific.uv.es (test zone) [OK] BDII: isn04.ific.iv.es (ATLAS production) [OK] PROX: lcg2proxy.ific.uv.es [OK] Non-Functional Time None Scheduled Down Time * Scheduled Maintenance During the Reporting Period None * Scheduled Maintenance During the Next Reporting Period None Major Operational Issues Encountered During the Reporting Period None
        Speaker: Sanchez, Javier
      • INTA-CAB 15m
        Speaker: Huedo, Eduardo
      • LIP-LCG2 15m
        Weekly Operations Status Report: LIP Reporting Period: 11/07/05 to 17/07/05 Availability of Core Services Hosted in the Site ================================================== RB: rb02.lip.pt LCG-BDII: ii02.lip.pt (problems has to be reinstalled) LFC: se01.lip.pt Non-Functional Time ==================== [OK] 7 days Points to Raise at the Operations Meeting ========================================= The site has been upgraded to LCG2.5.0 LFC version is the latest (1.3.4), this is the recomended catalog to be used for the swetest vo. Scheduled Down Time =================== Major Operational Issues Encountered During the Reporting Period ================================================================ Upgrade to Scientific Linux 3 (or equivalent) ============================================= All nodes in SLC305 Points to Raise at the Operations Meeting ========================================= open bugs 3617 none bifi n/a replication failed 2702 none ifae n/a Job submission failed 2258 biomed pic 2005-04-22 Got a job held event, reason: Unspecified gridmana... 1909 biomed cnb.uam 2005-03-21 GlueSARoot losed for biomed VO [GGUS ticket#3544] RGMA -(UPV-GRyCAP)- 2nd E-mail about this problem This one is complicated, I have sent a mail to rollout, and no answer up to now two other sites with the same problem.
        Speaker: David, Mario
      • IFAE 15m
        Speaker: Borrego, Carlos
      • PIC 15m
        Speaker: Borrego, Carlos
      • UAM-LCG2 15m
        Weekly Operations Status Report: [ UAM-LCG2 ] Reporting Period: [ 09/07/05 ] to [ 15/07/05 ] Availability of Core Services Hosted in the Site ================================================== MyProxy [OK] VOServer [OK] RB [OK] BDII [OK] Non-Functional Time ==================== none Scheduled Down Time =================== none Major Operational Issues Encountered During the Reporting Period ================================================================ none Upgrade to Scientific Linux 3 (or equivalent) ============================================= By when will all service nodes in the Site be upgraded? [when the LCG-2_6_0 is OK for Quattor.] By when will the WNs in the Site be upgraded? [when the LCG-2_6_0 is OK for Quattor. ] Installation with QUATTOR (without yaim) Points to Raise at the Operations Meeting ========================================= none
        Speaker: Pardo Navarro, Juan Jose
      • UB-LCG2 15m
        Speaker: Graciani, Ricardo and Casajus, Adrian
      • UPV-GRyCAP 15m
        Weekly Operations Status Report: [ UPV-GRyCAP ] Reporting Period: [ 11/07/05 ] to [ 15/07/05 ] Availability of Core Services Hosted in the Site ================================================== RB, BDII: apis.dsic.upv.es -> Some power supply problems. Non-Functional Time ==================== - Total days unavailable: 0 days Scheduled Down Time =================== * Scheduled Maintenance During the Reporting Period - Total days unavailable 0 * Scheduled Maintenance During the Next Reporting Period - Estimated number of days for which the site will be unavailable 0 days Major Operational Issues Encountered During the Reporting Period ================================================================ GIIS Error: dn: GlueSARoot=dteam:dteam,GlueSEUniqueID=aker.dsic.upv.es,Mds-Vo-name=grycaplcg2,mds-vo-name=local,o=grid str2entry: invalid value for syntax 1.3.6.1.4.1.1466.115.121.1.27 We have tried to find the problem, but we can’t understand what happens. This error appears and disappears without any reason. Upgrade to Scientific Linux 3 (or equivalent) ============================================= By when will all service nodes in the Site be upgraded? Already done (SL 3.0.4 & FC2) By when will the WNs in the Site be upgraded? Already done (FC2) Points to Raise at the Operations Meeting ========================================= none
        Speaker: Caballer, Miguel
      • USC-LCG2 15m
        Weekly Operations Status Report: USC Reporting Period: 09/07/2005 to 15/07/2005 Availability of Core Services Hosted in the Site ================================================ None Deployed Non-Functional Time =================== None Scheduled Down Time =================== None Major Operational Issues Encountered During the Reporting Period ================================================================ None Upgrade to Scientific Linux 3 (or equivalent) ============================================= By when will all service nodes in the Site be upgraded? Already there By when will the WNs in the Site be upgraded? Already there Points to Raise at the Operations Meeting ========================================= None
        Speaker: Saborido, Juan
      • BIFI-LCG 15m
    • 12:10 → 12:15
      APEL Status Report 5m VRVS

      VRVS

      APEL STATUS REPORT == Period == From July 9 to July 15 == Status of each SWE site == Site: CESGA Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: CNB Solved Problems of Last Report: NO Missing Accounting Entries: None Publishing User Name Information: Since 30/06/05 they are not publishing this information Actions: Solve the problems with the user name information Other Comments: None Site: CIEMAT Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes. April 15 have not published the user name. Actions: None Other Comments: None Site: ifae Solved Problems of Last Report: NO Missing Accounting Entries: Since 23/06/05 Publishing User Name Information: NO. The last published data has not this informatation Actions: Solved Problems of Last Report. JoinProcessor Reprocess Other Comments: None Site: IFCA Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: IFIC Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: INTA Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: LIP Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: NO. The last day they have republished all their data without this information Actions: None Other Comments: None Site: pic Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: UAM Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: UB Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: UPV Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None Site: USC Solved Problems of Last Report: Yes Missing Accounting Entries: None Publishing User Name Information: Yes Actions: None Other Comments: None == Accounting Support == Accounting Web Page: http://www.egee.cesga.es/EGEE-SA1-SWE/accounting/ Accounting FAQ: http://www.egee.cesga.es/EGEE-SA1-SWE/accounting/faq.html Accounting Statistics: http://www.egee.cesga.es/EGEE-SA1-SWE/accounting/reports/ CPU Normalization: http://www.egee.cesga.es/EGEE-SA1-SWE/accounting/normalization.html Accounting Guides: http://www.egee.cesga.es/EGEE-SA1-SWE/accounting/guides/ Contact e-mail: egee-admin@cesga.es
      Speaker: Rey Mayo, Pablo (CESGA)
    • 12:15 → 12:30
      Action lists 15m VRVS

      VRVS

      Speaker: Pacheco, Andreu (IFAE)
      • 5.1.17.8 CNB to upgrade Apel version 3.4.39-1 (PENDING) 15m
        Speaker: Lopez Cacheiro, Javier (CESGA)
      • 5.3.7.4 Mario to deploy gmdat monitoring tools in SWE (OPEN) 15m
        Speaker: David, Mario (LIP)
      • 5.5.30.1 CNB, UB, UAM, IFCA, IFIC, PIC, USC to activate fmon agents in the WNs 15m
        * Fco. Bernabé reporting. * Instructions how to activate the FMON agents in the CESGA EGEE Monitoring web site.
        Speaker: Fco. Jose Bernabe (CESGA)
    • 12:20 → 12:35
      Preproduction Activity Status 15m VRVS

      VRVS

      This section will contain an update about the preproduction activity in SWE where more and more sites will be involved.
      Speaker: Pacheco, Andreu (PIC)
      • PIC Report 15m
        Speaker: Carlos Borrego (PIC)
        more information
      • CESGA 15m
        Speaker: Lopez, Javier (CESGA)
      • IFIC 15m
        Speaker: Fernandez, Alvaro (IFIC)
      • LIP 15m
        Speaker: David, Mario (LIP)
      • INTA 15m
        Speaker: Neuffer, Kai (CAB-INTA)