Speaker
Mirko Pojer
(CERN)
Description
16 days are allocated in March 2016 to prepare the machine for the beam. Around 7000 powering tests will have to be performed to re-commission the superconducting circuits. An extensive list of tests will have to be executed as well on the various systems affected by interventions during YETS. A preliminary planning for these tests will be shown.