GIF++ installation and schedule meeting
from last meeting:
THIS WEEK GIF OPEN. As planned:
Monday pm : open concrete blocks and start opening false floor
Tuesday am: open roof
Friday am: close roof and false floor
-BEAM Roberto: Beam time requests submitted. Total 4 periods 3,3,2,2 weeks each
-COSMIC TRIGGER
-Installation of cosmic trigger chambers on-going
-WATER COOLING
EN-CV has requested to postpone the installation. They are not ready before December 7.
SOURCE "DUTY-CYCLE":
-General reminder to all users that the source must be on as much as possible. If someone is putting off the source is his/her responsibility to:
.Inform all gif users using the elog
.restart the source at the end of the access
.In general long access or periods with source off must be requested and discussed during the Wednesday weekly meeting.
.Source scan can be done only on Thursday
.before any change the Run coordinator should be informed (for the moment Armando, 164257)
.email for source status implemented (by Sylvain). Please let me know if someone would like to receive
.Phone for Run coordinator requested.
-ABSORPTION FACTOR
-absorption factor need to be discussed for each side (upstream and downstream). Setup responsible should prepare their requests for gamma flux (very urgent!)
-GAS DURING XMAS
-Roberto will ask to EN-MEF (Mats, David) the plan for shutdown of gas supply during Christmas
Proposed date December 15.
-AIR CONDITIONING
-On-going discussions for beam trigger and air conditioning. Waiting news from EN-MEF (Adrian, Ilias): I know there is some meeting where CMS (Wolfram) is involved (but I'm not officially in the loop)
-BEAM TRIGGER
-Which sort of trigger do we need? Waiting news from Weizmann and Technion institutes.