AWAKE BTV decisions

Europe/Zurich
865 1-D17 (CERN)

865 1-D17

CERN

Description
1) Choice of screen material for AWAKE BTVs with expected delivery dates (Stefano/Bart) 2) Reduction of radiation levels for BTV.412426 – how low can we go (ALARA) ? (Gerhard) 3) Work remaining for assembling new BTVs (Gerhard) 4) Installation dates for 4 remaining BTV detectors (Gerhard) a. BTV.412350 b. BTV.412353 c. BTV.412426 d. BTV.412442 (BTV SPS) 5) Installation and commissioning dates for electronics (Stephane) 6) Remaining spending for phase #1 (protons) during 2016
    • 1
      Choice of screen material and expected delivery dates
      Speakers: Bartolomej Biskup (CERN), Stefano Mazzoni (CERN)
    • 2
      Discussion
    • 3
      Radiation level expected for BTV.412426
      Speaker: Gerhard Schneider (CERN)
    • 4
      Discussion
    • 5
      Production of new BTVs
      Speaker: Gerhard Schneider (CERN)
    • 6
      Installation dates for BTVs
      Speaker: Gerhard Schneider (CERN)
    • 7
      Remaining spending for AWAKE BTV system (phase#1)
      Speaker: Stefano Mazzoni (CERN)