      Approval of the minutes 5m
      Speaker: Julie Coupard (CERN)
    • 16:05 → 16:10
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 16:10 → 16:25
      LIU-SPS ECR SPS-V-EC-0005 (EDMS 1709399) Modification of the SPS sectorization in long vacuum sectors (arcs) 15m

      Installation of 11 new sector valves (VVSA). New 11 gauges (Pirani and Penning) have also to be installed. Two new VVR (roughing valves) per new sector (22 total) have to be installed.

      Speakers: Chiara Pasquino (CERN), Jose Antonio Ferreira Somoza (CERN)
      ECR
    • 16:25 → 16:40
      LIU-SPS ECR SPS-JHCAA-EC-0001 (EDMS 1719396) Construction of concrete support structure for new LIU beam dump in SPS ECX5 15m

      The new SPS beam dump to be installed in LSS5 in LS2 needs a support structure, part of which will be cast in the 2016/17 EYETS below the existing platform. This ECR describes the work to be carried out in the EYETS.

      Speakers: Alejandro Martinez Selles (CERN), John Andrew Osborne (CERN), Richard Francis Morton (CERN)