LIU - Planning & Installation meeting

→ Europe/Zurich
864/1-C02 - indisponible a partir du 24/04/2017 (CERN)

864/1-C02 - indisponible a partir du 24/04/2017

CERN

50
Show room on map
    • 16:00 → 16:05
      Approval of the minutes 5m
      Speaker: Julie Coupard (CERN)
    • 16:05 → 16:10
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 16:10 → 16:25
      LIU-IONS LEI-LJ-EC-0001 (EDMS 1746651) Space Reservation Request - LEIR Dump Installation 15m

      Space request reservation for the implementation of a beam dump for the LEIR machine.
      The new dump for the extracted beam will be installed in the LEIR injection and extraction line (direction PS to LEIR), at the exit of magnet ETL.BHN10, near the end of the bi-directional LEIR transfer line ETL.

      All changes are foreseen to be implemented during the YETS 2017-2018.

      This SRR is part of the LHC Injectors upgrade (LIU) framework, which regards the LEIR machine, to meet the goals of the LIU Ions luminosity in LHC.

      Speaker: Chiara Di Paolo (CERN)
      SRR
    • 16:25 → 16:40
      LIU-PS SRR PS-LJ-EC-0005 (EDMS 1746714) Space Reservation Request - PS Ring Ralentisseur 15m

      This document describes the future possible locations for the PS ralentisseur, to be installed during the Long Shutdown 2 (LS2).

      Speaker: Giulia Romagnoli (CERN)
    • 16:40 → 16:55
      LIU-PSB ECR PSB-ACWFB-EC-0001 (EDMS 1733551) The New PS Booster RF System 15m

      The existing PSB RF system is composed of three different groups of cavities (C02, C04 and C16) covering distinct frequency ranges and distributed in 4 straight sections of the PSB machine (5L1, 7L1, 10L1 and 13L1). All the existing equipment will be removed and replaced by a single wideband system paced in three straight sections (5L1,7L1 and 13L1). As for the existing systems, the surface components will be placed in BRF1 and BRF2 equipment rooms.

      Speaker: Mauro Paoluzzi (CERN)
    • 17:10 → 17:15
      AoB 5m