GIF++ installation and schedule meeting
-
-
09:15
→
09:20
Review of last week operation 5m
-
09:20
→
09:25
Plans for today (source scan) & next wednesday access 5m
Source Scan @ Thursday (today):
--------------------------------------------Source ON 1h, then short access for 30 minutes (Barbara)
Filter Scan downstream : 14h-18h CMS-CSC
Filter scan upstream : evening 3hPlan for next week :
---------------------------TUESDAY : (2.5.)
We open the bunker in the morning, (and some floor tiles).
Detector installation by Beatrice.
GEM1, GEM2 and CMS-CSS move out of clear view for Henso.Wed-Thu : Reserved for Henso. NO WEDNESDAY ACCESS, NO FILTER SCAN downstream.
FRIDAY:
Opening of the bunker. Preparation of the Muon Beam time.
-
09:25
→
09:45
Beam Schedule 2017 20m
-
Report from Downstream Field 5m
-
Report from Upstream Field 5m
-
-
09:45
→
09:55
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
-
09:55
→
10:10
Infrastructure & Upgrades to the Facility 15m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)Ongoing Projects :
- Upgrade of GIF Control System - Initial list submitted to DT controls group
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
Temperature at GIF 5m
Status / Plans / Interventions to address the low temperature problem currently seen inside and outside the bunker area
Speaker: Giuseppe Pezzullo (CERN)
-
10:10
→
10:20
Announcements 10m
-
IMPACTS for 2017 5m
Guidelines for filling in IMPACT requests
Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). If your work is outside, please state the whole number of hours. -
AOB 5m
Any Other Business
Gas bill 2016 : please note that the EP-DT budget for GIF does not cover consumables.
Gas used at the GIF++ will have to be paid by the consumer. We will start the TID's soon.Question from Barbara : How is the Argon/CO2 provided, and will this be charged to the user.
To be clarified with Roberto & Fred.O2 contamination study - Roberto to comment.
-
-
09:15
→
09:20