    • 16:05 → 16:10
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 16:10 → 16:25
      LIU-SPS ECR SPS-LJ-EC-0005 (EDMS 1698074) New RF power feeder line in SPS point 3 shaft (PA3) and GT10 for LIU-SPS 15m

      This ECR is part of the LHC Injectors upgrade (LIU) framework, which covers SPS, and seeks to prepare the reliable delivery of the required beams to the LHC, to meet the goals of the High Luminosity LHC (HL-LHC) project.

      Part of the SPS upgrade project concerns the upgrade of the 200 MHz RF system, which is the frequency at which main accelerating system of the SPS operates. This involves the addition of two new travelling-wave cavities and the construction of two new RF systems which will feed them, as well as the installation of the surrounding equipment to ensure the correct functioning of said systems. The required changes are divided in several parts with related ECRs to describe the changes in surface, shaft and the tunnel.

      The corresponding SRR has been already approved [1].

      This ECR is dedicated to the required changes in the shaft (PA3) and in the GT10 for the upgrade of the 200 MHz RF System.

      Speakers: Eric Montesinos (CERN), Pilar Parrado Caballero (Ministere des affaires etrangeres et europeennes (FR))
    • 16:25 → 16:40
      LIU-SPS ECR SPS-ADKSV-EC-0001 (EDMS 1835539) Slotted Line Kicker in LSS3 of the SPS 15m