Ranko Ostojic28/01/2010, 17:00The goal of the LHC IR Upgrade Phase-1 is to provide more flexibility for focusing of the LHC beams in the ATLAS and CMS high luminosity insertions and to enable reliable operation of the collider at a luminosity above the nominal 1034 cm-2s-1. This improvement is achieved by replacing the present low-b triplets and D1 separation...Go to contribution page
-
Maurizio Vretenar28/01/2010, 17:25Summary of the LINAC4 project planning (including eventual required upgrades in the injector complex – PSB and PS), summary of the commissioning plan and the expected performance level and challenges (including the injector complex – PSB and PS), presentation of a time line for the expected–planned performance levels (bunch intensity and brightness versus time).Go to contribution page
-
Stephane Fartoukh28/01/2010, 17:50The goal of the LHC Insertions (IR) Upgrade Phase-I is to enable a reliable operation of the machine with a performance at least doubled with respect to its design luminosity. One key ingredient is ideally a reduction of b* down to 25 cm, using a new inner triplet (IT) with longer NbTi quadrupoles operating at a lower gradient (~120 T/m) and therefore offering a...Go to contribution page
-
Stephan Russenschuck28/01/2010, 18:20The design work of the MQXC quadrupole magnets for the inner triplets is constrained by the baseline planning for the LHC-PP project, its co-funding by the European Union (PF-7), the suppression of superconducting cable development (using existing stock of LHC dipole cable), and the in-house production of the series magnets (with tooling recovered from the LHC production lines). Nevertheless,...Go to contribution page
-
Ed Ciapala28/01/2010, 18:45200 MHz capture cavities and feedback system upgrades, criteria for identifying upgrade needs and lead-time for taking decisions on the upgrades options for preparing Crab cavity installations in IR4.Go to contribution page
-
Ralph Assmann28/01/2010, 19:10Phase 2 collimator jaws, Cryo collimators and eventual required additional tertiary collimators and absorbers. Main milestones and deadlines for decision taking (e.g. what choice for the secondary collimators etc.). Strategy and time estimate for installation and commissioning of the new collimation system.Go to contribution page
-
Sylvain Weisz28/01/2010, 19:35Planning of the various installation work in consideration of the space requirements, radiation levels, existing and missing infrastructures, alignment and survey, coordination issues for upgrade (e.g. collimation upgrade versus IR upgrade and impact of LHC general consolidation work on the LHC upgrade projects. Options for implementing some of the upgrade work already before the extended...Go to contribution page