The new beam dump system to be installed in LSS5 in LS2 needs the enlargement of the ECX5 downstream tunnel eye.
This ECR describes the preparation work to be carried during the YETS 2017-2018 for the partial re-routing of three cable trays to free the space needed for the civil engineering activities foreseen during LS2.
Speakers:
Etienne Carlier
(CERN),
Georgi Minchev Georgiev
(CERN)