      Approval of the minutes 5m
      Speaker: Julie Coupard (CERN)
    • 16:05 → 16:10
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 16:10 → 16:25
      LIU-SPS ECR SPSVC-EC-0003 (EDMS1884358) Temporary modification of 3 QD short straight Sections configuration for aperture restriction assessment 15m

      Horizontal aperture scans detectes a systematic asymmetry in the aperture at the level of the QD short straight sections all around the SPS machine: this limitation could explain the measured losses with high intensity 25 ns proton beam and Q20 optics at the injection flat bottom.
      A temporary replacement of 3 QD eccentric drifts in position 10110, 11310 and 40110 with an eccentric drift OD159/ID156 mm is proposed in order to eliminate the most severe restrictions and test the impact on losses during the 2018 run.

      Speaker: Chiara Pasquino (CERN)
    • 16:25 → 16:30
      LIU-SPS ECR SPS-MKE-EC-0002 (EDMS 1872486) Upgrading of kicker magnets of the SPS west extraction system, MKE6 5m

      The three kicker magnets of the SPS LSS6 extraction kicker system (MKE6) will be exchanged for upgraded versions. The existing kicker magnets have serigraphy on the surfaces of the ferrite yoke facing the beam: each serigraphy finger has a length of 200 mm.
      The upgraded kicker magnets are nominally identical, except that the length of each serigraphy finger is reduced to 180 mm. The reduced length will approximately half the beam induced heating of the ferrite yoke, associated with 25 ns beam.

      Planned during YETS 2017-2018.

    • 16:30 → 16:35