Within the framework of the LIU – SPS beam dump system upgrade, LSS1 will be reconfigured starting from half period 116 up to half period 119. The document describes the detailed vacuum layout of this part of the SPS ring.
As part of the LIU-SPS project, the SPS internal beam dump will be relocated from SPS LSS1 to LSS5 during LS2. This ECR summarises the modifications in BA1 surface building induced by the removal of the horizontal and vertical kicker high voltage pulse generators and their electronics and controls.