MEDICIS coordination meeting
26-1-022
CERN
MEDICIS Coordination - 19 July
Eric - Vincent - Roberto - Kevin - Valentin - Laura - Moazam - Julien - Thierry - Giordano - Philippe - Pascal - Elodie - Fabio
MED011 : Er169 separation
source transfer :
3 spectroscopies done : Tivek Er169 : 100kBq --> exposed to powder inside glass vial; 7Be : 3 kBq 22Na : 100Bq
Philippe : complicated spectra for to other spectro, will be delivered end of the week
Thursday : no pumping possible
Target 631 M : coupling Ok - Evaporation of acid 1.5ml : Paper in target cone displayed only some counts
Friday : strong outgasing - interlock 1e-4mBar for heating. left 24 hours to outgas.
Monday night : could get 1 st beam (2uA total, Ca+ was seen at previous Er collection); electrode was outgasing during HV ramp up. Sign that something is condensed on electrode.
Tuesday : final set-up : 150nA total current.
Now: current read-out in foil+ collimator ~ FC read out.
loss in collimator is 7%.
Application mass scan to check.
Control of power converters : mag converter tripped 2x on tuesday.
Separation was working over night--> wednesday
Tuning of beam : 168Er found at same magnet current as last time.
Ratio 168:169Er was about 1:10 (Roberto thinks 1:100)
Sample implantation and retrieval done by Pascal
Container #4 could not be used : issue with pulling cap O ring?
Container: #5 was used instead : Foil # tbc Implantation on 1 foil.
Retrieval : 12mSv/h at contact
collective dose : 0uSv
Camera : collection chamber : cannot use camera image in screen used for collections.
Slit software needs calibration : to be confirmed by Christophe (& Vincent) - interface .
Spectro : Er169 : measured overnight yesterday - results beginning next week
less than 100MBq was collected, 10-20MBq can be expected (from the integrated current on ).
Where and how long are the data saved : This need stop be logged in timber.
shipment foreseen to Rotterdam. tbc . Will find out.
MD : 149Tb irradiation & separation
Pumping Ta644M. are now on shelves.
target positioning tomorrow.
This afternoon:
target change 631M —> shelves
644M —> Front End for outgasing and electrode check.
to confirm if purge water goes to the sink. should be corrected : Alexandre Broche/Jean Marie Vuallat.
NPL ? No news from NPL for shipping back : This urgent.
Container #4 : 2 foils : installation in chamber tomorrow by Moazam.
plug target on Front End is 649M for this week end.
149Tb spectro : tuesday
August planning : 155Tb/149Tb collections then shipping NPL/Lausanne
Lab :
25 July : Ventilation stop : all activities stopped.
Maintenance/Lab activities : 30st-3rd August
laser shielding installation :
Phone antenna : corridors/Hv room/
impact (EN EL Pawel)
13-17th paint in laser room :
order the key and put in Traka. (Julien will follow up).
20-24 August : resin on floor in MELISSA Lab.
Laser Table arrives : in September
meeting on laser activities : check tomorrow for meeting.
electrical installation in laser room : plans are sent to Rene.
AOB :
electrical installation : S1/S2 : ambiant dose is OK.
Target 645M is calibrated : to prepare for importation of 155Tb and other from Gd target irradiated in Arronax.
Roberto : isotope inventory and ratio
in September : source importation
11C separation.