MEDICIS coordination meeting

→ Europe/Zurich
26-1-022 (CERN)

26-1-022

CERN

MEDICIS Coordination - 19 July

Eric - Vincent - Roberto - Kevin - Valentin - Laura - Moazam - Julien - Thierry - Giordano - Philippe - Pascal - Elodie - Fabio

MED011 : Er169 separation

source transfer :

3 spectroscopies done : Tivek Er169 : 100kBq --> exposed to powder inside glass vial; 7Be : 3 kBq  22Na : 100Bq 

Philippe : complicated spectra for to other spectro, will be delivered  end of the week 

Thursday : no pumping possible

Target 631 M : coupling Ok - Evaporation of acid 1.5ml : Paper in target cone displayed only some counts

Friday : strong outgasing - interlock 1e-4mBar for heating. left 24 hours to outgas.

Monday night : could get 1 st beam (2uA total, Ca+ was seen at previous Er collection); electrode was outgasing during HV ramp up. Sign that something is condensed on electrode.

Tuesday : final set-up : 150nA total current.

Now: current read-out in foil+ collimator ~ FC read out.

loss in collimator is 7%.

Application mass scan to check.

Control of power converters : mag converter tripped 2x on tuesday.

Separation was working over night--> wednesday

Tuning of beam : 168Er found at same magnet current as last time.

Ratio 168:169Er  was about 1:10 (Roberto thinks 1:100)

Sample implantation and retrieval done by Pascal 

Container #4 could not be used : issue with pulling cap O ring?

Container: #5 was used instead : Foil # tbc Implantation on 1 foil.

Retrieval : 12mSv/h at contact

collective dose : 0uSv

Camera : collection chamber : cannot use camera image in screen used for collections.

Slit software needs calibration : to be confirmed by Christophe (& Vincent) - interface .

Spectro : Er169 : measured overnight yesterday - results beginning next week

less than 100MBq was collected, 10-20MBq can be expected (from the integrated current on ).

Where and how long are the data saved : This need stop be logged in timber.

shipment foreseen to Rotterdam. tbc . Will find out.

 

MD : 149Tb irradiation & separation

Pumping Ta644M. are now on shelves.

target positioning tomorrow.

This afternoon:

target change 631M —> shelves 

644M —> Front End for outgasing and electrode check. 

to confirm if purge water goes to the sink. should be corrected : Alexandre Broche/Jean Marie Vuallat.

NPL ? No news from NPL for shipping back : This urgent.

Container #4 : 2 foils : installation in chamber tomorrow by Moazam.

plug target on Front End is 649M for this week end.

149Tb spectro : tuesday

 

August planning : 155Tb/149Tb collections then  shipping NPL/Lausanne

 

 

Lab : 

25 July : Ventilation stop : all activities stopped.

Maintenance/Lab activities : 30st-3rd August 

laser shielding installation : 

Phone antenna : corridors/Hv room/ 

impact (EN EL Pawel)

13-17th paint in laser room : 

order the key and put in Traka. (Julien will follow up).

 

20-24 August : resin on floor in MELISSA Lab.

Laser Table arrives : in September

meeting on laser activities : check tomorrow for meeting.

electrical installation in laser room : plans are sent to Rene.

 

AOB :

 

electrical installation : S1/S2 : ambiant dose is OK.

 

Target 645M is calibrated : to prepare for importation of 155Tb and other from Gd target irradiated in Arronax.

Roberto : isotope inventory and ratio 

 

in September : source importation 

11C separation.

 

 

There are minutes attached to this event. Show them.
    • 11:00 → 12:00
      Coordination 1h

      feedback MED011: Ta631M 169Er separation
      prep MD: Ta644M irradiation - 149Tb collection
      AOB