Speaker
Andy Butterworth
(CERN)
Description
o Keywords:
- IST, cold check-out, time lines, settings management, tools, slip stacking
o Points to be addressed and questions to be answered:
- Planning from IST to cold check-out across the injectors (including Linac3) with special focus on the SPS
- Definition of time lines for different implementation phases towards operational system
- Address settings management and the status of available tools including requirements and milestones for new developments
- What are the lessons learnt from Linac4, PS LLRF issues (missing references), SPS 800 MHz commissioning and how will they impact the 2019/20 activities?
- Detailed time line and milestones for slip stacking commissioning.
- How can the SPS cavity test stand be exploited to test controls,…