GIF++ installation and schedule meeting

Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 09:35
      Review of last week operation & plans for this week 20m

      Weekly summary and plan for the next week :

       ------------------------

      ALICE :   Campaign comes to an end.
                         In total a slot of one week is needed to perform the test on a batch of 5 chambers.

                        Tentative : week 15

      ATLAS-MM :  SM1-M3 installed in bunker at 2.9m upstream. 4 week irradiation planned.
                               Space in front reserved for LM1 - will come in 2 weeks.
                               Universal trolley to arrive end of April. Tentative to be placed in current CMS-DT location.
                               GC to be used next week.   Source scan planned every 1-2 days for 1.5h (20-2.2).

      sTGC : QS2  (electronics) + QS3 (HV test) taken out.
                   4 chambers arrived at CERN,  next week to placed inside the bunker (2 in the corridor), two for irradiation.
                   Test will be ≈ 1h.

      EP-DT2  :  no news

      CMS-RPC :  Installation of two trolleys planned. One for longevity test and the other for testing the electronics in order to launch the mass production.  One  installed, one (cosmic trigger) to be installed earliest next Wednesday.
      In this time frame  we foresee to do the tests with the (upstream)  earliest during the week  of the 7th of April. They will last  2 weeks maximum.  Sunday or Monday ≈ 1h access planned.  Today access after the meeting. 2h source OFF scan  (included in Access).  Source scan 2h - 6.9 today after lunch. Gas flow needs to be checked, as we are on the limit.

      EcoGas  - Setting up the dedicated mixer.


      Otherwise : 2.2 filter for most of the week.

      =====================
      CMS-GEM 1&2 : Happy

      EP-DT1: Requests - constant field on Tuesday (abs. 1)

      ATLAS-RPC  :  5 gaps from mass production installed. Will be changed to contain less flammable material.

      CMS-DT MB 1&2  :  Test on the mono-tubes still on going. Preparing for the de-cabling of both chambers expected starting next week. Removal planned for the 1st or 2nd week of May.

      LHCb : preparation to exchange chamber.  Installing it next Wednesday (not done).

      CMS-CSC:  Continuing radiation and recovering the setups from the preparation area.
                        
                          

    • 09:35 09:40
      Mass Production Tests & Long Term Campaigns - General Items 5m

      General planning for long term campaigns.

    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

       

      Upcoming BE-BI : test of  XBPF in 100Gy steps. Starting soon.

    • 09:50 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      Ongoing Projects :
      =============

      Correction of Irradiator Signals after power cut.
      Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.

       

      PyTIMBER :

          Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • LS2 restrictions & interventions 5m
      • Bunker Extension Project 10m

        News about the ongoing bunker extension

        Bunker extension :

        ==============

        Bunker layout frozen, work started already.

        Two VICs done yesterday.

        Currently estimated start : Either early July or early September.  (before or after August)
        If we want July, we have to push now.

    • 10:00 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

         

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2019 !

      • New Announcements 5m

        !!! AUL test needed on WED 13/03 !!!

        In principle we are not concerned, due to the fact that are not related to our infrastructure. Anyhow, to be sure we would announce to you, like that, in case we will have a power cut, you can react as soon as possible.

      • AOB 5m

        Issue with ligth.  Button near access door should enable the light for additional 2h.
        We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLE

        Locked door on Saleve side.
        Proposal top remove the cylinder to avoid the guard locking the door during night times.  -> Cylinder HAS BEEN REMOVED