Weekly summary and plan for the next week :
------------------------
ALICE : Campaign comes to an end.
In total a slot of one week is needed to perform the test on a batch of 5 chambers.
Tentative : week 15
ATLAS-MM : SM1-M3 installed in bunker at 2.9m upstream. 4 week irradiation planned.
Space in front reserved for LM1 - will come in 2 weeks.
Universal trolley to arrive end of April. Tentative to be placed in current CMS-DT location.
GC to be used next week. Source scan planned every 1-2 days for 1.5h (20-2.2).
sTGC : QS2 (electronics) + QS3 (HV test) taken out.
4 chambers arrived at CERN, next week to placed inside the bunker (2 in the corridor), two for irradiation.
Test will be ≈ 1h.
EP-DT2 : no news
CMS-RPC : Installation of two trolleys planned. One for longevity test and the other for testing the electronics in order to launch the mass production. One installed, one (cosmic trigger) to be installed earliest next Wednesday.
In this time frame we foresee to do the tests with the (upstream) earliest during the week of the 7th of April. They will last 2 weeks maximum. Sunday or Monday ≈ 1h access planned. Today access after the meeting. 2h source OFF scan (included in Access). Source scan 2h - 6.9 today after lunch. Gas flow needs to be checked, as we are on the limit.
EcoGas - Setting up the dedicated mixer.
Otherwise : 2.2 filter for most of the week.
=====================
CMS-GEM 1&2 : Happy
EP-DT1: Requests - constant field on Tuesday (abs. 1)
ATLAS-RPC : 5 gaps from mass production installed. Will be changed to contain less flammable material.
CMS-DT MB 1&2 : Test on the mono-tubes still on going. Preparing for the de-cabling of both chambers expected starting next week. Removal planned for the 1st or 2nd week of May.
LHCb : preparation to exchange chamber. Installing it next Wednesday (not done).
CMS-CSC: Continuing radiation and recovering the setups from the preparation area.
introduction, goal of the test, plan, needs
Improvements needed or planned for the facility.
New Items :
==========
Ongoing Projects :
=============
Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.
PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only
News about the ongoing bunker extension
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
NEW IMPACT needed for 2019 !
Issue with ligth. Button near access door should enable the light for additional 2h.
We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLE
Locked door on Saleve side.
Proposal top remove the cylinder to avoid the guard locking the door during night times. -> Cylinder HAS BEEN REMOVED