ATLAS - sTGC : Currently no chamber installed. 8 Chambers should arrive tomorrow.
2 needs to be tested on Saturday. 1 QL1 is critical to be tested & installed.
CO2 flow issues during the last months. Interlock changed, currently working, but needs follow up.
ATLAS-MM : 2 chambers in setup behind CMS-CSC installed - will leave for Christmas.
One chamber installed for long term irradiation test near source LM2 (Pos,D02).
Discussion : Possible installation of 1 full assembled sector in Upstream. ≈ Feb. for 2 months.
Will be clarified in the coming weeks.
CMS-CSC: Irradiating sing last week. Friday afternoon - requesting stable conditions.
Setup from preparation area to be moved (bunker upstream or Bld. 904).
EP-DT1: Setup moved of 25 cm closer to the source. Until Christmas.
EP-DT2 : Request to have the default value 2.2 in upstream.
GC would be needed for the next 2 weeks.
CMS-DT: Rails back installed. Long one fixed to floor, other to be done.
Electronic racks needed mid-November. Chamber expected to be installed around February.
EcoGas : Will be switched off for Christmas / no flushing.
CMS-RPC : iRPC and Trolley 1& 3 in bunker. Small trolley with iRPC installed.
ATLAS-RPC : Small prototype installed on October 23rd still taking data.
Big setup with ATL-RPC gap will be installed next week on Wed DEC 04th.
LHCb : working on the irradiated prototypes removed from GIF++ some months ago.
Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
---------------------------------------------------------
Stop of Gas supply for 7.01 to 10.01 !
Gas usage during Christmas announced.
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
---------------------------------------------------------
Next Irradiator maintenance : Proposal - January after Christmas Closure.
introduction, goal of the test, plan, needs
BLM measuring campaign announced / ≈ 100 BLM, 3 days approx. First half of 2020 ?
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)
Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
Improvements needed or planned for the facility.
Upcoming :
=============
PRIMARY & RAW WATER 2/2
• Status
– CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.
– BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
– BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).