Present:Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne. 

Matter arising

  • From MKP temperature prediction looks like 12h scrubbing beam should be OK, needed to sort out some checks and also about the SIS interlock level into LSA, to be included in the Operational deployment discussion
  • RF function FESA class to sort out for high level SW, Andy will sort this out.
  • TI2 survey strategy to be presented today in LMC, has been sorted out with ABT with OP. Presently situation is OK, but prefer to have it done if possible, although the last 350 m does not cover the larger features requiring most corrector strength. Slides sent around this morning.

Tomography in the SPS (Giulia)

  • Initial look at SPS tomography in 2007 showed would be useful but that the long co-axial cables were an issue. Needs optical fibres.
  • Would be useful for slip-stacking, phase calibration and voltage calibration. 
  • Proposed solution has been worked out, sharing at the moment with the bunch length measurement HW and SW. Still some HW and SW needed for this, list given.
    • FESA Class to be extended
    • GUI to be adopted
    • wall current monitor for beam profiles (APWL, bw < 3 GHz)
    • Fibre optic link (fibre, transmitter, receiver)
    • Extension of sampling pit, including remotely controlled variable attenuators
    • Digitization of profiles (ADC)
    • Trigger devices
    • Synchronize to cycle and RF
  • Main issue is that the co-axial cable not good enough, Fibres exist but need the transmitter and receiver. No technical solution yet in place. FB section is looking at this and are optimistic that a solution will be found.
  • Need also new solution for digitisers, for longer term separate system. Other systems as well since end of life.
  • Propose also to have a brief FS document, summarising the requirements (Giulia to draft).

Dry runs and test progress news (Kevin/Verena)

  • See links for details

Updated dry run planning (Kevin/Verena)

  • Re-visited the planned dry runs to sort out what is still possible in the present situation
  • For ALPS now waiting for full ring installation, working on the interlocking part, depends on FESA + HW
  • W18 RF generation tests, damper, rephasing. Needs input from Philippe.
  • W19 RF ions FFA etc.
  • W22 FGC tests only make sense if back at CERN

Status of integration of beam dump system in CCC (Eric)

  • Status given for SIS interfaces, about half are not yet available. Being brought up gradually. Missing from SBDS permit the Vac from PVSS, but not sure it's needed.
  • Status defined for the GUI, signals defined. 
  • TSU expert application which will be available for OP.
  • For SBDS control need 4 FESA classes, 2 of which are available, 2 new ones being developed, versions will be available soon. Etienne mentions that for the class Tank the temperatures are not direct, only on the mirror supports at the outside. Question also whether pressures should come from ABT or VSC? Problem with the sampling frequency from PVSS....organise a discussion (Etienne/Chiara/Eric).
  • Question whether SIS should be surveying the early dump is correct in terms of min/max? Eric replies that this is now sorted out by the application. To be sorted out (Eric with OP and ABT).
  • Question on the air flow interlocking? Confirmed that SIS is only surveying the air flow. No BIS input from the dump. as requested by EN/STI.
  • In conclusion in good shape, still missing some FESA classes and documents, in contact with ABT for this.

AOB 

- Shutdown planning, 2 months extra from RF for transmission line installation, needs revision with ACE and the FSU coordination, since can be optimised. Action Eric/Julie/J.P.Tock

Next meeting: 22/4/2020 (Kevin)

Draft agenda

  • Draft planning for the restart & known additional delays David
  • Final MKDV switch performance Francesco
  • Beamline installation status Antonio Antonio
  • RF diagnostics interface for the CCC Luci
  • RF power limits, update Ivan
  • References settings and measurements Anthony