LIU-SPS Machine Coordination Meeting 06/05/2020
Present: Alexander Huschauer, Alexandre Lasheen, Anthony Rey, Antonio Grande Mallavia, Brennan Goddard, Chiara Pasquino, David Mcfarlane, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier, Fabio Follin, Francesco Maria Velotti, Giulia Papotti, Hannes Bartosik , Ivan Karpov, James Ridewood, Johan Dalla-Costa, Jonathan Meignan, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Luciana Kolbeck, Philippe Baudrenghien, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain, Wolfgang Hofle, Yannick du Borgne
Matters arising and actions
- Julie has brought the concern about the WP2 activity on the critical path to the LS2C, should be arbitrated this Friday, details later from David.
- Update on MSC actions mentioned in David's list, details later from David.
- Average RF power calculations per cycle, confirmed possible by Verena.
- Early Dump class, Eric/Nicolas M have been in contact and this is progressing.
- BA1 BPMs in optics sequence confirmed up to date in the gitlab repository.
- SPS rampup time from T0 with HWC, OP team in place, will come back in about 3 weeks with first draft. Question on whether LEIR commissioning could be advance, need to discuss but constraints from the source and Linac.
News on dry-run and test progress
- Will be part of the overall rescheduling now there is a firm date for T0, working on all of this.
- Need to clarify how many people can be in CCC for these special occasions, since need a certain number of people. CCC seems to be treated differently from rest of CERN, at the moment being followed only in OP. Bren to raise with Rende and ATS management, since should not cripple other activities.
Status on schedule update (David McFarlane)
- All MSC works has been moved to Step 2
- In Step 1 leak detections including TI2 and TI8
- WP2 fire safety works will start on 18/5
- BA3 access point only limited works possible without main company on site
- Analysis being made now of feasibility of the dates as communicated by EN/ACE, which assumes groups are back at full speed from start June
- Many items where dates are contingent on contractors, EN/EL and EN/CV especially, dates almost certain to slip but not clear by how much.
- LSS5/BA5 has a lot of uncertainty around the contractors
- General question of how to deal with the planning items where we know the assumed date is wrong, but have no idea of what the real date will be....add 'contingency', or block in colour a fixed assumed period of 1 month?
- Review of all this by groups in May
- By 12th June LS2 day should have the fuller picture and feedback from all groups and contractors, with a consolidated planning.
References settings and measurements (Anthony Rey)
- Project scope is central place to store screen-shots, files, settings that could be used as reference
- Able to handle Java objects
- Improved search tool
- Interfacing with other OP tools with API
- Tried to create something with BE/CO for support/maintenance, to avoid problems seen in past with logbook, inspector etc.
- Aimed at NXCALS,
- Concepts in place and strong synergy with the elogbook. Lack of resources in OP is now handicapping the progress.
- Now need to define future of this project and integration with CO, long term support, NXCALS, etc.
- CO have said they can provide support for this from LS3 (sic) onwards
- Action needed to assure the development and support for this, between CO and OP groups (for IPP).
Round table/AOB
- Fabio announces first version of BLM concentrator, and data being sent to SPSQC, not yet the event builder.
- Eric will present something in 2 weeks for Early Dump
- For ions have written down commissioning steps for LEIR
- Will next week have a detailed look at the checklist for ions, and review of philosophy of L3 stripping foils
Agenda for next meeting
- PS to SPS longitudinal transfer: few slides on status, plans, tools, simulations and MD (Ivan/Alex/Elena/Heiko)
- Plans for 200MHz cavity measurements (Christine)