LIU-SPS Coordination Meeting
Vidyo
LIU-SPS Machine Coordination Meeting 06/05/2020
Present: Andy Butterworth, Anthony Rey ,Antonio Grande Mallavia, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti , Giulia Papotti ,Gregoire Hagmann , Hannes Bartosik , Ivan Karpov, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Luciana Kolbeck, Philippe Baudrenghien, Nico Madysa, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain, Yannick Le Borgne.
Matters arising and actions
Kevin is working on input for the 2021 beam commissioning schedule. The requirements of the LIU MDs is being incorporated as well to be discussed at the various committees. Philipp asked when the schedule for next year will be decided. Verena replied that after the 8th June, where the LHC experiments will come up with their requirements for 2021, and the 12th of June where the end of the HWC for the various machines will be stamped, the 2021 injector schedule will be prepared. So by end of June this exercise should be finished.
News on dry-run and test progress
Kevin report on the re-scheduling of the dry runs. Dry runs on ALPS interlocks and FGCs are foreseen for the month of June in the CCC and the required PPE.
Status on schedule update (D. Mcfarlane)
David presented the status of the current schedule. The proposal for SPS LS2 with the closure date on 4th of December still seems to hold. The irradiated cable campaign in BA2 and the beam dump in BA5 are on the critical path and feedback is still awaited from EN/EL for BA2. Etienne and Jonathan added that the beam dump is not more or less on the critical path than it was before the COVID. COVID has not deteriorated the situation. The readiness of the dump core is the driver for the end of SPS LS2. Antonio reported on the status of the beam line installation and vacuum sector closure. 2 more sectors will be opened in June and July. 67 out of 97 sectors are closed. Next week the old baseline will be caught up. Brennan commented that starting HWC the week before the Christmas stop is not ideal due to the time lost for ramping down and ramping up after Christmas again. Stephane added also that in case HWC started only after Christmas the conflict with the BA6 CV maintenance and mains testing could be avoided. David mentioned that it would make sense to have the DSO test before Christmas and start HWC only after Christmas. Brennan reported the start of a discussion on an additional week for PSB beam commissioning due to the Christmas stop now in their beam commissioning period. The SPS is welcoming this proposal to defend moving the HWC start after Christmas and if the all the other beam commissioning periods are simply shifted. Stephane asked when the discussion on the PSB beam commissioning would take place. Gian Piero was to organise a discussion.
Optimisation framework for the SPS (N. Madysa)
Nico presented the contents of a collaboration with CO for a generic optimisation framework, hardware improvements for machine learning and storing neural nets in the control system. He then summarised the various efforts in the last two years for numerical optimsation, machine learning and reinforcement learning in the SPS and what will be provided for the SPS start-up. Francesco mentioned that he is working on using UCAP for deploying machine learned algorithms in the control room for the SBDS dump pattern analysis. Eric asked whether anything will be available in JAVA and how operational all these things will be? Verena replied that in industry most of the ML tools and algorithms are available in python and that at CERN we would like to profit what is available outside and not want to rewrite everything. UCAP and other means should however be exploited to make call python from JAVA. She also said that one of the main goals of the collaboration with CO is to provide operational solutions and move away from the proof-of-principle solutions only. Giulia added that bunch length optimisation for AWAKE and setting up of RF gymnastics should also be added to the list of applications to be provided for the start-up. Elena remarked that the bunch length optimisation tool for AWAKE should only be established together with the AWAKE collaboration to guarantee optimum results.
Optics and layout respositories (H. Bartosik)
Hannes reported on the current status of the SPS information in the layout database and the common optics repository. All ECRs are incorporated except the one on the 216 impedance reduction with moving BPMs etc. He also showed the interface to the aperture information in the layout database which can be used to generate sequences with. Verena mentioned that the optics aperture web viewer links should be made available in the control room. Verena and Brennan discussed the LHC commissioning tool that showed the trajectory in the injection region with beam envelope in the aperture. The aperture information should be made easily available through JMAD such that such a tool can be prepared for the SPS.
AOB: early dump surveillance SIS (E. Veyrunes)
Eric presented the additional SIS interlocks to ensure the correct early dump min/max settings for a given cycle. These were proposed to mitigate possible issues/inconsistencies with generation and drive. In addition the FESA class needs to reject inconsistent early dump, min/max settings. N. Magnin has agreed to that already. The SIS interlock relies however on correct timing information. SPS OP will discuss in the future how to ensure consistency of the timings.
Agenda for next meeting
- News from beam dump system Etienne
- Dry run planning Kevin
- IST planning David
- HWC planning Stephane
- 2021 planning (commissioning, physics, MD) Kevin