LIU-SPS Coordination Meeting

→ Europe/Zurich
Vidyo

Vidyo

LIU-SPS Machine Coordination Meeting 27/05/2020

Present: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne. 

Matters arising and actions 

BE/CO elements should all be ready, but main issue is the readiness from the equipment groups of things like FESA classes. Mainly under control but a few things to be sorted out. List being compiled by OP, will then make sort presentation in LIU-SPS MC meeting of readiness of both CO and all other components (Marine/Verena)

News from beam dump system (Etienne Carlier)

  • Status at start of lockdown documented in codimd page https://codimd.web.cern.ch/-KKQdIBiTfG5Bov7iVoZQA
  • LSS1 also strongly linked. Vac sectors all closed, magnets re-installed, now doing busbars and connections and ending cabling campaign. Overall 90% done.
  • LSS5 has still 3 cabling campaigns, 1 started, 2 to start. Need removal of scaffolding, CV installation to start, kicker platform and beamline installation. 
  • Some constraints - LSS5-ECX5 cabling is blocking other activities, and scaffolding removal.
  • Problems with cabling include co-activity in tunnel-eye, and supervision from ABT.
  • CV still do not have confirmed date for restart of activity, need to have pipes under the shielding before w27 (when cabling ends), for installation of skid in w28. Material is there, not the main driver,  waiting for EL to remove scaffolding.
  • TIDVG5 should be ready for installation on 20/10/20. Bakeout will be needed during the SPS closure for ISTs of access/Fire detection. Dump ready for operation on 08/01/21. Need to check if there is any interference for dump works if SPS closed 2 weeks before Christmas (Etienne/Stephane).
  • Kickers, vacuum, BI, all OK
  • Activities restarted, no blocking points, detailed planning being assembled
  • TIDVG core readiness is critical path
  • All groups confirmed manpower and priority is to EN/EL for cabling
  • CV schedule to confirm, try for this before 12 June.

Dry run planning (Kevin Shing Bruce Li)

  • Dry runs, soon tests can be made
    • RF optics upload, settings for different parts, start soon.
    • FEI a long list of things to do in June. Participants known, if CCC access is needed.
    • FGC for late June, lots of things to check, including SIS.
    • ALPS for early July - need to foresee NXCALS, post-mortem tests possible.

HWC planning (Stephane Cettour Cave)

  • SPS will close 4th Dec with patrol on 7th Dec. Note these dates might still slip. Tbc 12/6/20
  • Draft planning of system readiness dates
  • Discussed with main groups, key points are:
    • BA6 cooling will stop for 4 days in W50/51, requested by ATLAS. Waiting feedback CV
    • CO services all ready in July for dry-runs, except SBDS
    • EPC all OK, a lot of pre-requisites. Will not be able to run in BA6 if CV are doing the maintenance
    • Interlocks should all be OK end September
    • Aux PS waiting reply from EPC
    • RF 200 MHz power, all ready and conditioned from 21/12/20, but from start August for LL. Note that dates are preliminary and cannot be confirmed until end June, David to note this very clearly for 12 JUne LS2 days.
    • RF LL and SW, all slipped by 12 weeks, check new planning (Kevin + RF teams)
    • Beam stoppers etc all OK for start Dec (to check TCDIL - Stephane)
    • Kickers, septa, SBDS all ready for OP 14-26 Feb 2021.
    • Vacuum all ready for OP from 4/01/21
    • DSO tests in SPS from 8 - 10/12/20, then beam chain 7/4/21. For LHC will be 21/1 to 8/2/21 with LHC (tbc). Still to plan DSO test for TT20/NA
    • Access tests should be 2-8/11/20, and for CCC on 4/12/20
    • Fire Safety global IST week 44 (26/10/20)
    • From OP, beam to TED on 13/5/21, NA setting up 5/7/21 and physics 19/7/21
  • For question of start of HWC before/after Christmas, 3 dates still being discussed (4/12, 8/12, 4/1). If no additional week in 2021 will lose 0,1,2 weeks respectively.
  • Discussing with safety teams to keep the machines in 'technical stop' over Christmas, which means we should not have the double overhead.

2021 planning (commissioning, physics, MD) (Kevin Shing Bruce Li/Verena Kain)

  • Preliminary planning, based on Montreux version
  • Extra time added for RF capture (moved beam based alignment 1 week later)
  • First client is going to be AWAKE, good for shaking out everything
  • Beam to TEDs on 13/5/21
  • Moved LHC extraction setup to scrubbing stocking-fillers
  • Overall 6.5 weeks of beam comm.
  • Gives outline of 21 schedule. Rearranged to try and fit everything it. 3x AWAKE runs of 2 weeks each, 3x HiRadMat of 1 week each.
  • Ions to LHC as of November, big challenge. 2 weeks now of dedicated ion commissioning, with LL and slip-stacking. Decision point end w39, on whether with slip-stacking or backup 75 ns. Baseline remains slip-stacking.
  • Add list of constraints, like 'no MD in parallel with HiRadMat and AWAKE, etc.'
  • Look offline at whether MD should be planned with HiRadMat, and swapping last LIU-protons for HiRadMat (Kevin et al.)

AOB

  • Tomoscope, components within spec are available on the market, FB section looking into it: looks OK technically.
  • AWAKE have analysed bunch length stability, and would like this improved for 2021. RF investigating, time might be needed for 

Agenda for next meeting

  • Status on schedule update David
  • Update on power interlocking for RF Ivan/Elena
  • ISTs planning checkpoint Julie/Antonio
  • SPSQC status Verena/Fabio
  • FEI/FII testing: requirements, how, check list procedure, longer term: how to automate testing? Part of FEI application? Luci

 