LIU-SPS Machine Coordination Meeting 03/06/2020
Present: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne.
Matters arising and actions
Run through Minutes:
- Marine and Verena to present readiness of CO --> agenda for next week; list still being prepared
- Beam dump still had some concerns about co-activities; Etienne says that second cabling campaign will start next week; both campaigns will take place simultaneously as planned; dump core readiness could have an impact on schedule if SPS closed as planned; being looked at together with EN-STI. Date to be kept as announced by EN-STI for now. There will be a review of the readiness end of August (DATE)
- List of dry runs to be provided to Rende (ACTION: Kevin)
- Caveat was mentioned for David to take note of RF power upgrade schedule impact
- RF coordination meeting is taking place to advance on planning for RF (ensuring coherence of the different RF teams) in preparation for LS2 days where a full planning will be presented by Erk
- Stephane to add TCDIL to beam stoppers readiness; Stephane checked this. One question on calibrations still needs a confirmation for being ready. LLRF planning was received from Philippe.
News on dry-run and test progress
- Roman is not needed for the moment to help with the FGCs; what is much more critical is the delivery of parameters from David Nisbet; Stephane mentioned all parameters of the FGC-91 were deleted; the LSA integration with Makerules and Value generators had to be redone. Verena stressed that at some time Roman will have to be included. Stephane said that at the moment even LSA is not in a ready state. A refined dry run planning with more granularity is currently being prepared for the FGC tests.
Status on schedule update (David)
- BA1 beamline almost all ready;
- BA2 a-C coating final sector; LSS2 blocked for transport W24;
- BA3 access team back, ALPS connections ongoing, restart of power upgrade coming up; MC refurbishing with cavity conditioning is a concern;
- BA4 quiet, CV and EPC works on surface;
- BA5 beam dump installation;
- BA6 EPC works on surface and WP2 connecting to fire doors;
- VSC: new baseline with more detailed forecast; LSS3 closing dates under discussion;
- Schedule: BA2 final baseline still being defined, concern is irradiated cable campaign + 1 week of access system testing; BA3 RF, EN-HE and VSC being discussed; SBDS baseline defined --> likely to be the main driver for closure date;
- IST period: week 43 to week 49;
- Week 45 is entirely closed for access system tests; (ACTION: Etienne, David & co to cross check all safety aspects during WP2 tests);
Scrubbing planning (Kevin)
- AWAKE: re-phasing; controlled long. blow-up already needed for AWAKE; amplitude modulation needs to be ready as well;
- 4 weeks scrubbing priority + 2 week priority FT;
- End of 4 weeks: decision point how to continue with scrubbing;
Update on power interlocking for RF (Ivan/Andy)
- Summary of what is foreseen for power protection;
- LLRF produces alarm of power is clamped;
- Interlocks - dump the beam --> connection?;
- us time space power published by the LLRF;
- PLC system gives long term signals;
- OP modeling application to predict power levels --> to be discussed (ACTION: RF team to investigate how to present this to OP);
- Warnings and alarms should be in Fabio's application;
- Beam dump routing to FC (ACTION: RF team to ensure all connections and required interfaces are available);
- Temporary solution will be ideally replaced by full and final solution
- Action after beam dump: amplifiers will be tripped and they have to be restarted; how to unlock needs to be discussed;
- Observation buffers: alarms not used much in the SPS, SPSQC could include this by pushing PM some of the power limits; Heiko adds the idea is to see issues before something is going wrong. Big sister linked with SPSQC etc. - concept to be established. ((ACTION: OP & RF to agree on concept of operational scenario);
AOB
- Elena: AWAKE beam - will get come with an update;
- Etienne: one ECR still to be completed for CV installation in ECX5; connection of interlocking for beam dump to BIS is being re-investigated; need another cross-check that this is the correct approach (ACTION: Etienne to organize discussion on this);
- Julie: confirm closure date at 4th December and hand over to BE-OP; few remaining activities being clarified;
- Stephane: update for HWC, blocking point in BA6 all is okay with one more verification to make; mains are on good track; DSO tests NA dates are 8, 9, April 2021; tests for B-train will be ready for LLRF;
Agenda for next meeting
- IST feedback and planning David
- Status of turn-by-turn interlock with ALPS: visulisation, threshold management, etc. Kevin/Yannick
- Update controls readiness Verena/Marine