LIU-SPS Machine Coordination Meeting 10/06/2020

Present: Andy Butterworth, Anthony Rey ,Antonio Grande Mallavia, Brennan Goddard, David Mcfarlane, Elena Chapochnikova, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,  Giulia Papotti ,Hannes Bartosik , Ivan Karpov,  James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Kevin Shing Bruce Li ,Lars Jensen, Marine Gourber-Pace, Philippe Baudrenghien, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain,Yannick Le Borgne. 

Update controls readiness (Marine)

Marine summarised the status of control services for the SPS. All services are operational. Some hardware installations and timing cables still to come, e.g. for EPC in BA4 for end of June. It was clarified during the meeting that this should not have an impact on the IST testing in BA4 (Stephane mentioned that EPC ISTs in BA4 only start in July). OP had compiled a list of outstanding issues. Marine provided solutions and answers for all of them. RDA2 replacement for FESA classes is urgent. End of life 17th of June. CC7 migration and FESA upgrade to  3.7xx at latest by 10th of August. Action: Marine to provide Fabio and Kevin with list of FECs still not using CC7 and FESA classes still not 3.7xx. Issue of JDK11 compatibility with JavaFX components is being followed in CO. Action: Eric to send his additional findings of incompatibilities JDK11-JavaFX to Chris. Greg will provide thin library to provide additional information like Spare cycles of Normal cycles etc that was available in TGM-Concentrator. This will replace then TGM_CONCENTRATOR (deadline September). Action: Marine/Eric check with Greg whether also SIS logic provided.

Matters arising and actions 

Action remains on power interlock integration with OP. Action: Kevin organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. 

News on dry-run and test progress 

Dry run foreseen on the 16/6: First FGC test. Will take place in the CCC

Dry run foreseen on the 7/7: ALPS extraction orbit interlock BA6. Test BIS interlocking logic, GUI, LSA, FESA. Also, optics uploaded, try to test YASP with all available BAs.

IST feedback and planning (David)

David gave an overview of the updated IST planning, post-COVID. Tests are just starting. First IST coordination meeting took place last Wednesday. So far no issues like in other machines yet with water availability etc. Possibly first BI ISTs finished. Feedback to come still from Lars. Dedicated IST period will start on 19th of October. 2 weeks of machine closed in IST period for fire detection system (week 44) and access system (currently foreseen for week 45, to be confirmed).

Status of turn-by-turn interlock with ALPS: visulisation, threshold management, etc. (Kevin/Yannick)

Kevin presented the status of the integration of the ALPS interlocking: turn-by-turn interlocking and extraction orbit interlock. For turn-by-turn interlock connected to ring BIC in BA1 3 out of 4 BPMs per plane have to be operational otherwise the system interlocks continuously (is however maskable on the BIS side). BPMs cannot be disabled individually. FESA interface is being prepared. First versions of GUIs  by Yannick without FESA and LSA are also available with the main functionalities already visible. Francesco asked whether it would be possible to also add trends for the extraction orbit monitoring to see drifts or cycle-by-cycle variations. This will be added to list (Action: Yannick).  Action Johan: check with BI to configure logging of extraction orbit. 

AOB

Hannes/Francesco Layout DB news: aperture checks will be organised with OP. Transfer line sequences will also now be generateable from layout DB.

News from Beam Performance Tracking for the SPS. Several analyses already available. Kevin is working on the brightness exclusion plots for the injectors. First version already available.

Agenda for next meeting 

SPS performance tracking status Kevin/Johan

DSO test planning updated: scope and needs from equipment Stephane/James

RF FESA class readiness updates Andy

 

 