LIU-SPS Coordination Meeting
Zoom
LIU-SPS Machine Coordination Meeting 17/06/2020
Invited: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne.
Present: see attachment.
Matters arising and actions
- Marine has provided Fabio and Kevin with list of FECs still not using CC7 and FESA classes still not 3.7xx.
- Open action: Eric still to send his additional findings of incompatibilities JDK11-JavaFX to Chris.
- Open action: Marine/Eric check with Greg whether also SIS logic provided.
- Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. Elena mentions that RF are assembling details in EDMS document.
- Open action: Lars to give feedback whether BI ISTs finished.
- 2 weeks of machine closed in IST period for fire detection system (week 44) and access system currently foreseen for week 45 have been confirmed.
- Open action: Johan check with BI to configure logging of extraction orbit.
News on dry-run and test progress
- First FGC test on 16/6 took place in the CCC, after some initial access hiccups. Will have detailed presentation next week, was very valuable and good progress made. Will try to plan another iteration on Tuesday 23/6. Stephane thanked all the many people who worked to make this possible.
- Also made complete optics upload.
- Complete Dry-Run project file has been sent to Julie to integrate into the overall planning
2021 beams schedule proposal (Kevin)
- Kevin showed the schedule proposal for 2021 (will add a version number)
- BC W15, for 6.5 weeks, scrubbing, W26 for NA beamline setup, starting NA physics W28,
- MDs will start immediately.
- 4 AWAKE runs of 2 weeks, 4 HiRadMat runs of 1 week. AWAKE prefer Thurs-Tues to only have one long MD break, while HiRadMat want to start on Monday
- Maintain goals of p and ion beam, including commissioning FFA and slip-stacking and nominal ion beam. Shuffled the ion commissioning weeks and kept the 2 dedicated LIU proton weeks.
- Might still be last 4 weeks of year with NA ion physics.
- LHC pilot run not yet included, ideally would be W37 or W40. Presently know that it could be 1 week to 10 days, not before September.
- Agreed to put in explicitly the 2 days of full ion cycle for long injection plateau, as this is NOT MD. Would be 2x12h from physics, as well as W44 and W45.
DSO test planning updated: scope and needs from equipment (Stephane/James)
- Updated DSO tests, based on the new validated LS2 schedule.
- Ring tests (old chain 1) in 2 phases, 7-10/12/20 for the HW parts, then Beam tests from 7-10/4/21, which will be in full conditions. SBDS needed (not EIS but connected to BIS).
- Impact of SDBS, cannot arm the dump when the Ring 1 is in access. Problem will be how to make the W45 global tests with the SBDS which is not ready. Will be simulated for the first phase, then tested with final configuration in 2nd phase. Etienne confirmed that we can read the Access status bit from the SBDS, Eric asks for details for this, Etienne will provide them
- DSO tests of other chains will be done directly in real conditions in mid March. Need to close LHC P2 and P8, and will take 2 days. Being discussed with Joerg.
- For TT20 and North Extraction including ion interlock tests, planned with everyone for 7-9/4/21, in final conditions. Still to check details of BA80 ventilation. Reyes makes points that a 'light' DSO test for 4h is needed before FT ion run to validate the ion interlocking, should be added to schedule (Kevin).
RF FESA class readiness updates (Andy Butterworth)
- Update of last overview given in January.
- Generic FESA classes handling timing, functions and acquisition. Specific ones on cavity control, beam control and beam measurement
- Aimed to have final list of timing and functions by end March, still not complete despite extra time from covid. Only test devices for functions.
- Dashboard given with status, cavity control missing only 1T feedforward. Still missing much from beam control and measurement, late, specification with FESA interface still missing. Beam measurement mostly internal. Some other HW related stuff listed.
- For the milestones, shift by 3 months, and milestones will follow. Later ones are dependent on the HW deployment, including testing with the first cavities available. Surprising that the SW progress has all slipped 3 months and that no gain was possible wrt the planning.
- Kevin has a list of stuff he needs, including a list of function etc. for cavity control to be able to start preparing the LSA implementation. Anthony has question on the comb filter computing? Is this in firmware or LSA? Fabio mentions clock selection and asks where it is?
- Agreed to make another step in joint planning, Kevin/Verena to define from this what the detailed CCC plan will be, including dry runs etc, also to identify what information has to come from RF, and when, to include all these things. Presented next week in LIU-SPS MCM
AOB
- Optics upload direct from layout DB, worked well, two iterations, lots of cross-checks done and clean-up of elements listed in LSA. A few details to clean up. Available now for future testing for ALPS, RF. Thanks to all involved for the great work. Would now like to try for TLs. Anthony points out need to copy over the auto-tune correction per optics.
- Offline discussions held on how to progress with synchrotron tune, have a concept, ongoing.
- TI2 alignment coming back on the table, 12-18 week window.
Agenda for next meeting 24/6/20
- Dry run report (Stephane/Kevin)
- RF integration deployment milestones and planning (Kevin)