Invited: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne. 

Present: see attachment.

Matters arising and actions

  • Open action: Eric still to send his additional findings of incompatibilities JDK11-JavaFX to Chris - no reply yet from Chris.
  • Open action: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg
  • Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. Elena mentions that RF are assembling details in EDMS document.
  • Open action: Lars to give feedback whether BI ISTs finished. BI replied to David; David still to check full completion.
  • Open action: Johan check with BI to configure logging of extraction orbit. 
  • Open action: Kevin to add 4h DSO test.
  • Reaction to schedule: not much discussion on ions tests; rather questions where raised on potentially advancing delivery of FT beams to the target - 1 week earlier.

News on dry-run and test progress

Dry run report (Stephane/Kevin) 

  • Tests complete and successful for both FGC 63 and FGC 91
  • SIS tests:
    • There is still an incompatibility with the SIS when the states pass back to cycling; there will be a discussion on this this evening

RF integration deployment milestones and planning (Kevin)

  • Andy commented that the dates looks good for him; he confirmed that the cavity controller is available for testing; the only item that is still missing is the feed foreward
  • Injection settings still needs discussion; ACTION: Kevin to check with Andy

AOB

  • TI2 smoothing: strategy on aligning the full line including the last 350 m and what would remain to be done with the sequencing steps
    • TI2 alignment campaign was discussed; it seems that the last 350 m in the LHC are priority;
    • Next month vacuum will be opened; SPS has been asked to evaluate when full alignment could be done after LS2 in the next YETS (would need 18 weeks);
    • Meeting with VSC and SU was organized; still evaluating 18 weeks within LS2; SU could be available, bottleneck is whether we need to open vacuum; goal of management to open vacuum line; risk / probability for having to open vacuum is not known for now;  first measurement needs to be done that can tell whether the vacuum will have to be opened;
    • Would be good to have deeper analysis with patrick bestmann; Julie needs to know whether this scenario can still be discussed for within LS2; but it must fit into LS2 without compromising the closure date; to be checked also with Chiara;
    • ACTION: Julie to get update from measurement, and Chiara on impact for VSC; needs an analysis on probability that vacuum will have to be opened as well as its impact.
  • Cables for new interlocks of TIDVG: should not be forgotten to be negotiated with EN/EL, if any, for the new hardwired interlocks of the TIDVG water cooling and air cooling surveillance:
    • Better option for cooling would be to go for HW interlock; will get both for water and ventilation; still to be seen whether it will go tto BA5 BIC or via the WIC (more cumbersome to understand which is the fault); MPE and SMM are following this up; for cables still being investigated by SMM and MPE; no request for the moment.

Agenda for next meeting 1/07/20

  • TI2 smooting analysis and decision Patrick/Julie/Chiara
  • SPSQC status Fabio
  • 800 MHz for FT and ion beams: use cases Giulia
  • AOB: SPS ORA Bren

 

 