LIU-SPS Coordination Meeting
Zoom
LIU-SPS Machine Coordination Meeting 01/07/2020
Present: Andy Butterworth, Anthony Rey, Brennan Goddard, Chiara Pasquino, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti, Hannes Bartosik , Ivan Karpov, James Ridewood ,Johan Dalla-Costa, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Stephane Cettour Cave, Verena Kain, Patrick Bestmann, Julie Coupard, Marine Gourber-Pace.
Matters arising and actions
- Open action: Eric still to send his additional findings of incompatibilities JDK11-JavaFX to Chris - discussion with Felix this afternoon planned.
- Open action: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg
- Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. Elena mentions that RF are assembling details in EDMS document.
- Open action: Lars to give feedback whether BI ISTs finished. BI replied to David; David still to check full completion.
- Open action: Johan check with BI to configure logging of extraction orbit.
- Open action: Kevin/Rende to add 4h for ion DSO test.
- Open action: implications of sharing last week of scrubbing run between NA setting up and scrubbing.
- Open action: Jminuit not compatible with JDK11. Verena find other solution.
- Open action: Philippe/Greg H. do we need to start RF functions still 300 ms easier with new system?
- Open action: Marine to inform when CCC consoles to be moved to JDK11. Releases to be done in JDK8 or 11 for dry runs.
- Open action: James to find out how many people will be in the CCC for the access console installation.
News on dry-run and test progress
ALPS extortion orbit interlocking foreseen for 7/7. Technical discussions still ongoing due to possible modification of concept (continuous orbit interlocking). Possibly only test on 7/7: all BAs connected to YASP (with new cycle using new optics)
Next dry run to come: RF functions integration 14/7. Ideally have input already for 300 ms early start or not for RF functions wrt cycle.
Progress on RF diagnostics implementation with Giulia, Luciana and Kevin. Should be ready for upcoming dry run in August.
TI2 smooting analysis and decision (Patrick/Julie)
Patrick discussed the alignment situation of TI 2. The intermediate elements (dipoles) have not been re-aligned since 2007. It does not make any sense to re-align again only the quadrupoles. Entire campaign takes 18 weeks, could be squeezed to 12 weeks. Support from VSC needed in case of having to break the vacuum. (Horizontal and vertical alignment tolerances that vacuum system can still take in the order of 1 mm. More critical is alignment wrt to roll: tolerance of 1 mead.
Only the last 350 m were measured so far. Alignment of the quads should happen in the coming weeks.
Julie presented a first version of a planning taking into account as many constraints as possible: LHC cool down, powering, SPS HWC and beam commissioning, access system test, the associated vacuum sectors as well as access sectorisation and blast door for possible He propagation issues. Stephane mentioned that access through BA6 in week 44 (fire system test week) cannot be guaranteed as indicated in Julie's planning currently. Julie answered that the survey activities planned for this week will be swapped with activities that need access from BA7. Chiara remarked that due to the long vacuum sectors in TI 2 pump down could be significantly longer than 2 weeks. Only one slot of 4 weeks (+ 2 or more weeks of possible vacuum pump down) is currently planned in 2021. All the rest including the survey of intermediate elements could fit into 2020. The slot in 2021 would take too much time way from EPC ISTs in TI2 and cannot take place at that moment. It should be moved to after the HWC and check-out period where it fits with LHC powering tests for access to TI 2. Action (Julie, Verena, Jörg): find a possible slot for the remaining 4 weeks of survey activity in 2021. Julie will come back with an update on the current planning including all the feedback next week.
AOB: SPS ORA (Brennan)
Brennan introduced the operational readiness analysis meetings held for each machine: 4-5 hours of discussion on status of integration, operational scenarios, commissioning steps, overall preparation and software readiness and also weaknesses in current mode of operation or systems. Other machines give feedback and the final outcome is presented to the IPP. SPS ORA date to be scheduled beginning of October 2020.
AOB: Roundtable
Etienne reported on the progress of LSS5. Cabling campaigns are finished, scaffolding is being removed, piping beneath the dump is also finished, X-ray measurements to check piping ongoing, planning being sorted out for the re-installation of the beam line. BGI is late, cannot be installed before week 42. Impact is being studied. Eric V. reminded Etienne to send him the information on how to get the access veto information for the SBDS.
Chiara mentioned the work ongoing in LSS2. ZSs are back and the reconfiguration for impedance reduction at 218 and 216 (next week) is ongoing. The last AC coating intervention is finished.
David talked about recent issues with the new access system in BA2, where a guardian had to take over. All access points will be equipped with the new access system with BA3 being the last one to come next week.
Eric M. reported that all cavities are back in the tunnel in LSS3. No vacuum leaks were found.
Francesco informed that the 2 out of the 3 MKDHs have a larger aperture after inspection (instead of 2 with a smaller aperture). The aperture model is being updated.
James alerted that in the week of 13th of July the installation of the new access system console in the CCC will reduce the number of people allowed for other activities e.g. dry runs.
Agenda for next meeting 8/07/20
- Outcome of ALPS interlocking dry run Kevin/Yannick
- BLM status: injection, ring, transfer lines: integration, machine protection, logging Christos/Fabio?
- Logging status Johan
- TI 2 smoothing follow-up Julie
- MKP-L consolidation: Minimum amount of time for YETS/TS 21/22 Bren