LIU-SPS Machine Coordination Meeting 08/07/2020

Present: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne

Matters arising and actions

  • Eric has sent sorted out question of incompatibilities JDK11-JavaFX with Chris
  • Open action: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg
  • Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. Elena mentions that RF are assembling details in EDMS document.
  • Open action: Kevin/Rende to add 4h for ion DSO test.
  • Open action: implications of sharing last week of scrubbing run between NA setting up and scrubbing. 
  • Open action: Jminuit not compatible with JDK11. Verena find other solution.
  • Open action: Philippe/Greg H. do we need to start RF functions still 300 ms easier with new system?
  • Problem of compatibility with JDK11 has been fixed, assumed will be transparent - was tested OK. Some small mods needed to application
  • James has compiled information on how many people will be in the CCC for the access console installation.

News on dry-run and test progress 

  • ALPS dry run foreseen 7/7/20 could not take place, problems with FECs and too many BAs not running smoothly. BI working on this and YASP also being changed.Now plan end July for testing all BAs with ring interlocks.
  • Discussions on extraction interlocking still ongoing, will need dry in September
  • Useful RF dry run yesterday looking at synchrotron frequency including 800 MHz in LSA, found some problems with generation which are being fixed, will repeat and test soon.
  • Function FESA class dry run was for 14/7 but will advance to this week to check whether this is possible. 

TI2 smoothing follow-up (Julie) 

  • August/September measurement and alignment (if necessary) of main quads. Very low risk of opening vacuum.
  • From end September of December 2020 full smoothing of all intermediate sectors. 
  • Overall cost for SMM 85 kCHF, need to clarify that SMM have this budget.
  • Overall cost for VSC (in worst case) in 55 kCHF, with minimum number maybe 50% of this, This budget also needs to be found.
  • Bren makes point that this is purely exploitation activity and the budget was said by SMM to be available - needs to be found, as this 115 - 140 kCHF is NOT in the LIU project. Julie to confirm with SMM management that this funding exists.
  • No extra technical risk from VSC.
  • Can we stop after the quad alignment? LIU-SPS recommendation was to perform the full activity, under the assumption that the budget is available from exploitation from SMM.

MKP-L consolidation: Minimum amount of time for YETS/TS 21/22 (Brennan)

  • 18 weeks nominal, ABT can try and optimise to reduce this to 13-14 weeks. VSC might be also able to gain 1-2 weeks, and last 3 weeks can be done during HWC, would then mean 10 weeks needed with access, and 13 weeks beam total with 3 weeks in shadow of HWC.
  • Need to start the pumping before the Christmas vacation.
  • Need to communicate that 13 weeks are needed for MKP4L installation at end of 21/22, for October meeting. Not clear who is representing this - 
  • ABT to send the updated planning for MKP once we have validated the improvements in the conditions.
  • Keep pumping 4 weeks.

AOB

  • Request from VSC to add recabling of MST/MSE gauges, will be decided in LS2C.
  • ABP internal meeting for scrubbing run, two points came up, logging of vacuum readings at 1 Hz needed (in progress, Chiara), and acquisition of ecloud monitors (Fabio).
  • State machine of FGC3 different to before, causing problems for interlocking, discussing with EPC whether they can fix this. Seems like there has been a major change across the complex, OP are now dealing with the dependencies - being tested now with Eric and Quentin.
  • Meeting end of this week with RF about functions which need to be played before the start of the cycle (Kevin)

Agenda for next meeting 15/07/20

  • BLM status: injection, ring, transfer lines: integration, machine protection, logging Christos/Fabio
  • 800 MHz for FT and ion beams: use cases Giulia
  • Logging status Johan
There are minutes attached to this event. Show them.
    • 09:00 → 09:15
      Matters arising and actions 15m
    • 09:15 → 09:30
      News on dry-run and test progress 15m
    • 09:30 → 09:45
      Outcome of ALPS interlocking dry run 15m
      Speaker: Kevin Shing Bruce Li (CERN)
    • 09:45 → 10:00
      TI 2 smoothing follow-up 15m
      Speaker: Julie Coupard (CERN)
    • 10:00 → 10:15
      MKP-L consolidation: Minimum amount of time for YETS/TS 21/22 15m
      Speaker: Brennan Goddard (CERN)
    • 10:15 → 10:30
      AOB 15m