LIU-SPS Machine Coordination Meeting 15/07/2020

Present: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, Christos Zamantzas, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne

Matters arising and actions

  • Open action: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg --> check for end August; nothing critical, Greg is on vacation
  • Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. Elena mentions that RF are assembling details in EDMS document. --> to be scheduled
  • Open action: Kevin/Rende to add 4h for ion DSO test --> implemented on IPP slides; now hand over to Rende
  • Open action: implications of sharing last week of scrubbing run between NA setting up and scrubbing
  • Open action: Jminuit not compatible with JDK11. Verena find other solution.
  • Open action: Philippe/Greg H. do we need to start RF functions still 300 ms easier with new system? --> being investigated; foreseen to conclude by the end of the month
  • Open action: David to add Christos to list of invitees for IST meeting
  • Open action: SPS MCM to have an eye on a deadline for solving the hashtag issue in parameter names
  • Open action: Wolfgang to clarify with the LLRF team whether all HW requirements are met for 800 MHz slip stacking and whether system is ready in time for tests in 2021

News on dry-run and test progress

  • There will be two dry runs this week:
    • RF B-Train FESA interface is ready for testing; will check interface and functionality, different sources and modes (record, playback etc) on Thursday
    • RF FG tests for Friday, playing different supercycles and checking functions output on two channels

BLM status: injection, ring, transfer lines - integration, machine protection, logging (Christos Zamantzas)

  • Status update for BLM installation & integration
  • TT10 installations complete; all BAs work in progress; some minor issues; ISTs are in pipeline
  • Brand new FESA class developed (BLRSPS), running sums, missing data, reduced blind period during COAST; application already adapted; not yet RBAC protected; value generators are all ready
  • Interlocking strategy and integration in SIS ready
  • New naming convention agreed and migration ongoing
  • Update of layout DB ongoing
  • 5 diamond BLMs moving to new systems following the CERN and BI standards with new CPUs and standard BI cards; OP applications will need to be adapted to new FESA class
  • LHC type BLMs some upgrades; new monitor in LSS4; COLDEX class unmaintained
  • Questions:
    • Where are we with installations and ISTs? Is this on track? How done with David? --> ISTs - installations are being completed, from next week, by location and by test information will be provided to David (ACTION: Christos to bring information to David's meeting; ensure that Christos is on David's list of invitees)
    • BIS checks as part of IST? Would be good to get a quick status snapshot there. Where is this done? -- This is part of the IST; in fact, Christos reported that the full TT10 IST can be considered completed after this test, despite the initial concerns
    • Do we have all settings generated now already? Thresholds are deliberately wide open for the moment? The BLRSPS settings are all completed by Yannick. The BLMINJ still missing due to mods of FESA class. Christos said that the wanted to freeze this class by Monday next week.
    • SIS interlock adapted - dump of three consecutive cycle above threshold. Does this mean it's latched? It will interlock anyway, right? - The SIS will latch after three consecutive cycles dumped.
    • One the separator decision has been taken, how much time will we need to get the properties ready? Is this instantaneous? --> Would need to modify UCAP, BLMs need to have the good names, create parameters in NXCALs, maybe 100s of parameters; could be automated (from CCDE page); Fabio mentioned that from a virtual class publication via NXCALS works; deadline - we need to follow this up! If things don't move Fabio will check with CO and we may need to give a dealine; (ACTION: SPS MCM to follow up)
    • When are the DBLM FESA classes ready for OP to do the adaptations? - This should be coming in the next 2 months
    • Eric mentioned that he will not be able to make the SIS working before the vacation - cannot be used for ISTs; but should anyway not be part of the ISTs either.
    • Francesco asked about small mods - this concerns just the installation and topology. Modification on FESA class need to discussed with Francesco offline (ACTION: Francesco and Christos to look into).

Requirements for Operation of SPS 200 and 800 MHz systems with LHC icons after LS2 (Giulia Papotti)

  • LHCIONs 800 MHz requirements;
  • 800 MHz was originally not to be used for slip stacking; meanwhile it turned you that independent beam control would be possible with the 800 MHz and it would also be needed for ions beams during slip stacking to maintain stability at transition (clear indications from MDs done during 2018);
  • Transition is after FFA already;
  • OTDF also needed for ions operation now;
  • The lock to each group is done internally? Or we need to program something? Does the 800 MHz need to know whether we are in slip stacking mode? (ACTION: LLRF to see how they want to implement this - Elena mentioned that for the protons this is done automatically by the LLRF)
  • How do we deal with counter-phasing for the 800 MHz during slip stacking? This will not be possible.
  • Wolfgang: with respect to schedule, the implementation of this would be required for slip stacking tests - would need to be done for second half of 2021; Wolfgang expressed his concerns for the new 800 MHz system whether it is flexible enough to handle slip stacking as no further upgrades are foreseen. Normally, this should be able to handled (ACTION: Wolfgang to make sure this is all clarified in terms of HW)

Logging status (Johan Dalla Costa)

  • Checks to be done presented by Johan; goal to ensure all old variables have been successfully migrated to NXCALs.
  • Checks done automated via SWAN script;
  • Are we sure we have all parameters in that are interesting for us? --> the may variables used by other teams for logging (i.e., radiation doses) have been identified and will not be check by us (OP)
  • BLMs still being checked; not all through yet;
  • 9 TIDVG variables missing --> what to do here? (ACTION: Johan to check with CO once list is complete - report back second half of August)
  • Need to establish spreadsheet in variables checked | variables created

AOB

Agenda for next meeting 22/07/20

 