LIU-SPS Coordination Meeting

→ Europe/Zurich
Zoom

Zoom

https://cern.zoom.us/j/95974204283

LIU-SPS Machine Coordination Meeting 02/09/2020

Present: Anthony Rey , Brennan Goddard,Chiara Pasquino, David Mcfarlane, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,Gerd Kotzian, Giulia Papotti ,Ivan Karpov, James Ridewood ,Johan Dalla-Costa, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Luciana Kolbeck, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain, Wolfgang Hofle. 

Matters arising and actions

  • Open action: Kevin to clarify availability of total voltage measurement from LLRF
  • DONE: Verena to organize a meeting end next week for performance tracking and LHC fill statistics
  • Open action: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg --> check for end August; nothing critical, Greg is on vacation
  • Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. RF working on this, report expected for mid-September; Kevin suggested to discuss the operational handling of interlocks in August --> RF still preparing to finalize topic internally; will ask for reports in one month; then pick up on these
  • Open action: Kevin to check implications of sharing last week of scrubbing run between NA setting up and scrubbing
  • Open action: Jminuit not compatible with JDK11. Verena find other solution. Not before mid of October
  • Open action: Wolfgang to clarify with the LLRF team whether all HW requirements are met for 800 MHz slip stacking and whether system is ready in time for tests in 2021
  • DONE: WS parameter table to be prepared --> Hannes, Verena, James --> WS table essentially finished; want to be able to compare with linear WS; asked Federiko whether 1m/s is possible for cross-calibration; waiting for an answer; ions are in there; release as soon as info from Federico is there.
  • DONE: Philippe/Greg H. do we need to start RF functions still 300 ms easier with new system? --> being actively discussed now
  • DONE: Kevin/Rende to add 4h for ion DSO test --> implemented on IPP slides; now hand over to Rende
  • DONE: SPS MCM to have an eye on a deadline for solving the hashtag issue in parameter names
  • Open action: Verena/IPP ensure availability of CALS in read-only mode beyond LS2.
  • Open action: impact of installation of MKP-L and shorten run 2021. How much shutdown does the SPS need beyond EN/EL, BE/ICS and CV maintenance 2021/22.

Logging: Many holes in data moved from CALS to NXCALS. Decided to not carry on cross-checking NXCALS versus CALS data anymore. Too time consuming. Rely however on availability in read-only of CALS in case of missing data found in the future. --> action

David mentioned the discussion with LHC on Tuesday for the YETS 2021/22 planning. The end date can most probably not be moved anymore and is start of February for LHC check out (two weeks of check-out). The MKP-L exchange does not figure in the current discussion and does therefore not fit. The IEFC or similar need to approve it. 

News on dry-run and test progress 

ALPS interlock dry run being actively prepared with weekly meetings. Date is being finalised. Most probably 28th of September. 

Machine protection commissioning: first part (Verena)

Verena showed the first part of how to test the machine protection functionality of the machine protection system in the SPS. This first part was dedicated to the injection interlocking with the focus on the complex interplay of timing, interlocking, beam dump arming and the power converters of the MDSH and BHZ magnets. 

Verena proposed a BIC input jumper configuration during the beginning of the HWC before the beam dump is available remotely where the beam dump inputs on injection BIC and ring BIC are removed as well. This needs to be discussed with/communicated to MPE.

Eric mentioned that during the proposed testing phase 1 the SIS evaluation of the software permit defined by the FGCs should checked as well. It should be ensured that it allows BHZ pulsing. 

Brennan asked whether COAST has also been considered in all discussions (e.g. the behaviour of early dump etc). Etienne confirmed this. 

Etienne remarked that it is important that we have all the tools to check the sequence of the arming and involved timings.

Scraper specification (Eric)

Eric presented the specification summarising the operational requirements of the SPS scraper system. Various important parameters were put together, in particular also the number of required cycles per operational year. It was specified to 100k cycles.  It was discussed to further increase this number of have even more margin for MD.  Eric will follow up on this.

AOB: IST follow-up meetings - status (David)

David showed an overview of the ISTs already carried out across the machine. Everything is on track. James also shared the check list tool to see the ratio of already completed tests. Only a small fraction of ISTs are finished for the time being.

AOB: Follow-up on time shifted RFFGs (Giulia)

Giulia presented the issue as well as the various option that had been investigated. Various systems (the beam dump, PS for synchronisation) need RF functions to start before the start of the cycle. This was also the case in the past and was solved with an non-transparent patch at LSA drive. The two most promising solutions for the impacted functions (frev, frf, radial steering and gamm_t) are a transparent implementation in LSA or directly on the hardware. The most flexible solution is the LSA one that could also cover continuity between cycles if required (currently seems not to be required), but it also requires two timing events on the front end to trigger the start of the functions. The simplest is going via hardware where additional scalars would have to be defined that would be used to cover the time before the function is played. The proposal is to go for the hardware implementation and keep the LSA implementation (feasibility on the LSA has been demonstrated) as back-up. 

Heiko mentioned that in case things need to be modified in the future, the LSA option is much more flexible and a change would not impact as many layers. It should therefore be made sure that the LSA option remains a viable backup (two timing events for triggering functions,...).

 

The AOB on the ALPS extraction interlocks and the MKE pulsing was postponed to the next meeting.

 