LIU-SPS Coordination Meeting
Zoom
LIU-SPS Machine Coordination Meeting 09/09/2020
Invited: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne.
Present: see attachment
Matters arising and actions
- Done: Kevin to clarify availability of total voltage measurement from LLRF. Confirmed from PB that this will be available in digital and analogue
- Open action: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg --> check for end August; nothing critical, Greg is on vacation. Still no news.
- Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. RF working on this, report expected for mid-September; Kevin suggested to discuss the operational handling of interlocks in August --> RF still preparing to finalize topic internally; will ask for reports in one month; then pick up on these. Kevin to remind RF.
- Open action: Jminuit not compatible with JDK11. Verena find other solution. Not before mid of October
- Open action: Wolfgang to clarify with the LLRF team whether all HW requirements are met for 800 MHz slip stacking and whether system is ready in time for tests in 2021
- Open action: Verena/IPP ensure availability of CALS in read-only mode beyond LS2.
- Done: impact of installation of MKP-L and shorten run 2021. How much shutdown does the SPS need beyond EN/EL, BE/ICS and CV maintenance 2021/22.
- Open action: OP to check completeness of IST lists - Kevin/Verena/James/Stephane
Giula notes that there will be a functionality to disable the HW time-shifted functions.
Plots have been added by Kevin for the BPT, mirroring the information in the SPSQC.
News on dry-run and test progress
- Dry next Tues 15/9 to test 'Coast', making progress with the RF tests.
- Scheduled DR for ALPS interlocks for 28/9.
- Other tests ongoing.
Report from SPS RF Coordination meeting
- Discussion on scheduling of RF activities in 2021 last week triggered by scrubbing planning
- W15-21 for pLHC 25ns and pFT
- W22-30 multibatch LHC, scrubbing, intensity ramp up, pFT for NA physics, Setting up AWAKE beam
- W31-34 August
- W35-50 ions, MDs, FT ions physics
- Until W30 RF team will be very busy
- From mid-June could consider some stocking fillers on ion commissioning
- Long list exists of topics which could be ticked off
- Advancement of ion commissioning during p scrubbing will basically be opportunistic, depending on the system and beam advancement.
- Preparing an updated list to be able to go through the items in a structured way.
- Note that from September might be able to work on ions but beam only planned from W39, from rest of the ion injectors - early beam would be beneficial - check possibility (Reyes).
- Planning without any stocking fillers still needs to work, need to complete the plan in detail in the 3 weeks with beam (Giulia, Reyes)
- Main opportunity will be weeks 35-38 where will need the ion cycle, even without beam.
- Need to define needs for each week, in terms of cycles etc, Giulia.
Interleaving NA setting up with scrubbing in last scrubbing week?
- NA have asked to be able to start 1 week earlier with 'light' setting up during scrubbing, with option of another week of overnight scrubbing added.
- Will lose 1 week of daytime activity which is where we would have been doing 'cooldown compatible commissioning' (previously known as stocking fillers).
- One of the key activities is RF commissioning, difficult to quantify the time needed for all this new stuff, also OP stuff with things like extraction setup where we know well the time needed.
- Present plan for the 4 weeks scrubbing includes important activities for RF doing setting up of multibunch beams using low duty cycle.
- Detailed planning proposed for the scrubbing with daily breakdown and pre-requisites.
- Very busy and packed programme for SW2 and SW3 of scrubbing
- COLDEX needs access after the extraction is set up, end of first week - would be moved out 2 weeks later? Not very optimum since will generate losses - need to remove COLDEX at end of SWeek 2. Need to discuss with COLDEX people (Hannes, Kevin).
- TIDVG "commissioning", request for controlled conditions with high intensity beam, ramping up power with time for observation.
- End of SW3 should have multiple batches accelerated to 450 GeV
- SW4 would then be NA setting up in the day and scrubbing overnight, to improve and measure beam quality.
- Look at adding 4h mini-shifts in the day during the SW4 and SW4 (Kevin, Verena)
- Agreed that we can go for this ambitious plan, need to minimise impact of COLDEX.
Which LHC statics plots?
- LHC supertable was maintained as accelerator statistics page, with some limitations
- LHC team interested in joining the Beam Performance Tracking, where integrate the LHC needs into this.
- Injectors BPT would track LHC performance with time, no fetching of fillnumbers
- LHC will make the mapping between fill number and timestamps.
- Outline of functional requirements made, will follow up with Joerg and LHC teams, list can be added to.
ALPS extraction interlock and MKEs
- 2 evaluations before extraction to give extraction permit.
- ABT can reduce the 1st check to 8 ms for both extractions.
- 2nd check will be just before extraction, 1 ms or so.
- If not triggered, kickers will slowly discharge, which is a problem if not fully discharged before next extraction.
- Is there an internal check on kickers to see if fully discharged before the Resonant Charging? ABT are studying this now (Etienne/Francesco)
Round Table
- Interface working for RF beam control, development continues.
- BBQ interface being tested, also link to PM.
- For replacement of MDHB, study done, original support will be kept with an adaptor plate, to allow intervention in half a day. Looks feasible.
- Last Friday made dry run of the connection of the EDF signal if SPS needs to be cut by them.
- 3 Scenarios developed for MKP installation, being discussed.
- Stitched models for optics repositories now working, can try upload for SPS.
- Issue with SU resources for coordination for intervention to update extraction magnets in beamline, as fully occupied in PS
Agenda for next meeting (16/09/2020)
- Status of SPS SE spill control Verena
- AWAKE long. beam quality studies (data from 2018 and expectations for Run 3) Heiko/Ivan
- Hysteresis modeling integration Nico
- SPS weaknesses post-LS2 Verena