GIF++ installation and schedule meeting
Vidyo ONLY
CERN
-
-
10:20
→
10:40
Weekly planning 20m
WILL BE UPDATED DURING THE MEETING !!!
CoVid-19 Risk Assessment for the Facility : https://edms.cern.ch/document/2376286/1
General guideline :
- ONE setup to enter the bunker at any given time.
- All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
- Traceability of people on site : Logbook ! - List all the people you encountered.
- General access Wednesday is suspended for the time being
Electronic locks now activated in the preparation area + service area -> "GIF-ServiceArea" e-group)
----------------------------------TUE 13.Oct: New gas pipes installation starting till TUE 20th (IMPACT 161288)
WED 14.Oct. Test of Fire Alarm connections (Possible Power Cut) (IMPACT 162074 )
BLM measuring campaign announced / ≈ 100 BLM, 6h approx.
Week 43 (October 19th till Friday 23rd). We will arrange everything in a way that the setup could be installed inside the bunker in the upstream area near ATL-sTGC setup----------------------------------
ATLAS-MM :
SM1 long term chamber inside bunker (2-3 months). IC4H10 test ongoing. New batteries placed.
ATLAS - sTGC : Everything moved out of the bunker. Two boxes sent to bldg.180. Other chambers received to EHN1 and under CO2 flushing in the prep. area. After tomorrow's visit, one of the chambers received will be put inside the bunker and the mixture C5H12/CO2 will be switched ON.
CMS-CSC: Still some issue with the gas system. (O2 cell and H2O). New cell / sensor being ordered. 4. Nov. to be lowered.
EP-DT1: Measurements campaign is over and the setup is moved out (placed near the wall, Saleve side). Fe sources were been moved inside the safe.
EP-DT2 : Detector installed in the EP-DT2 trolley. The aging test with eco-friendly gas mixture are going well and the recover from the EN-EL maintenance is on going.
CMS-DT: Expected to return to bunker around end of November. INFN still blocking activity outside Italy.
EcoGas : New detector will be installed. After that the test campaign will be resumed using standard mixture (R134a, iso-butane, and SF6)
CMS-RPC : iRPC trolley removed and sent back to 194.
Radiation program resumed after the EN-EL maintenance.
Cosmic (scintillators) Trolley :ATLAS-RPC: Coming back end of October. Ageing test of modules. Might need to go in the upstream field.
ATLAS-sMDT : Installation of gas pipes (small cable tray) on October 7th. Done. Expected arrival date to the EHN1 is October 12th.
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1--------------------------------------------------------------------------------------------------
-
10:40
→
10:45
Long Term Planing - General Items 5m
Current estimated NA beam start : 12/07/2021 (2.5 months delayed)
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.- https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
- https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N
-
10:45
→
10:50
New requests for tests at GIF 5m
introduction, goal of the test, plan, needs
Bulgaria academy of science -> testing of new type of radiation monitor systemA new setup of ALICE-RPC will come. More news in coming weeks.
Lab on Fiber (LOF) dosimeter
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF) - 10:50 → 10:55
-
10:55
→
11:00
Announcements 5m
-
IMPACTS for 2020 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-
10:20
→
10:40