GIF++ installation and schedule meeting
Vidyo ONLY
CERN
-
-
10:20
→
10:40
Weekly planning 20m
WILL BE UPDATED DURING THE MEETING !!!
CoVid-19 Risk Assessment for the Facility : https://edms.cern.ch/document/2376286/1
General guideline :
- ONE setup to enter the bunker at any given time.
- All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
- Traceability of people on site : Logbook ! - List all the people you encountered.
- General access Wednesday is suspended for the time being
Electronic locks now activated in the preparation area + service area -> "GIF-ServiceArea" e-group)
----------------------------------TUE 13.Oct: New gas pipes installation starting till TUE 20th (IMPACT 161288) Ongoing
WED 14.Oct. Test of Fire Alarm connections (Possible Power Cut) (IMPACT 162074) DONE
BLM measuring campaign announced / ≈ 100 BLM, 6h approx.
Week 45 (November 2nd till Friday 6th ). We will arrange everything in a way that the setup could be installed inside the bunker in the upstream area near ATL-sTGC setup -> postponed until beginning of NovemberInstallation of roof mounting points (downstream area) -> now scheduled for next week Wednesday at 10h
29.10 Maintenance of gas detection for bldg. 909 - transparent
4. November - gas detection inside bunker - transparent
----------------------------------
ATLAS-MM :
SM1 long term chamber inside bunker (2-3 months). IC4H10 test ongoing. New batteries placed.
ATLAS - sTGC : One crate inside prep. area, 2 chambers inside. New creates arriving.
Move of support frame planned for Friday to make space for sMDT.CMS-CSC: Still some issue with the gas system. (O2 cell and H2O - planned for next week). 4. Nov. to be lowered.
EP-DT1: Measurements campaign is over and the setup is moved out (placed near the wall, Saleve side). Fe sources were been moved inside the safe.
EP-DT2 : Detector installed in the EP-DT2 trolley. The aging test with eco-friendly gas mixture are going well and the recover from the EN-EL maintenance is on going.
CMS-DT: Expected to return to bunker around end of November. INFN still blocking activity outside Italy.
EcoGas : New detector will be installed. After that the test campaign will be resumed using standard mixture (R134a, iso-butane, and SF6)
CMS-RPC : Small trolley being prepared. 70x70cm. To be placed.
Radiation program resumed on trolley 1.Cosmic (scintillators) Trolley :ATLAS-RPC: Coming back end of October (currently unknown due to CoVid situation).
Manpower currently at CERN could fill in.
ATLAS-sMDT : Installation of gas pipes (small cable tray) on October 7th. Done.
Frame should be moved to bunker on Friday.==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1--------------------------------------------------------------------------------------------------
-
10:40
→
10:45
Long Term Planing - General Items 5m
Current estimated NA beam start : 12/07/2021 (2.5 months delayed)
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.- https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
- https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N
-
10:45
→
10:50
New requests for tests at GIF 5m
introduction, goal of the test, plan, needs
Bulgaria academy of science -> testing of new type of radiation monitor systemA new setup of ALICE-RPC will come. More news in coming weeks.
Lab on Fiber (LOF) dosimeter
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF) - 10:50 → 10:55
-
10:55
→
11:00
Announcements 5m
-
IMPACTS for 2020 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-