GIF++ installation and schedule meeting

→ Europe/Zurich
Vidyo ONLY (CERN)

Vidyo ONLY

CERN

Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:20 → 09:40
      Weekly planning 20m

      WILL BE UPDATED DURING THE MEETING !!!

      CoVid-19 Risk Assessment for the Facility :  https://edms.cern.ch/document/2376286/1

      General guideline :

      • ONE setup to enter the bunker at any given time.
      • All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
      • Traceability of people on site :  Logbook ! - List all the people you encountered.

      Electronic locks now activated in the preparation area + service area ->  "GIF-ServiceArea" e-group)
      ----------------------------------

      BLM measuring campaign announced / ≈ 100 BLM, 6h approx. Week 45 (November 2nd till Friday 6th ). We will arrange everything in a way that the setup could be installed inside the bunker in the upstream area near ATL-sTGC setup    -> postponed until beginning of December

      Installation of roof mounting points (downstream area) -> now scheduled for 21.10 Wednesday at 10h  : DONE

      29.10 Maintenance of gas detection for bldg. 909 - transparent

      4. November - gas detection inside bunker -  transparent

      4 November: 

      9:30 Moving Katerina's detector in the prep zone @GIF

      ==> Removal of the legs of the trolley.

      ==> Replacing detector at original location

      -10:30 - moving our MM Quads in the prep zone in order to prepare it for the "hanging"

      -14:00 - Hanging procedure starts.

       

      ----------------------------------

      ATLAS-MM :
      SM1 long term chamber inside bunker (2-3 months). IC4H10 test ongoing. New batteries placed.
      3 long time chamber placed (currently on the ground). Lifting chamber to be scheduled 4 Nov.
      New IMPACT needed, safety visit needed for new setup.                      

      ATLAS - sTGC :  Proposal to have 3 test slots per week. Support frame moved to make space for sMDT.

      ATLAS-sMDT   :   Frame moved to bunker. Some noise problem currently under investigation.

      CMS-CSC:  Issue with cooling - solved.  Still some issue with the gas system.
      (O2 cell replaced.  H2Osensor under investigation).
      Setup to be lowered on 4. Nov.

      EP-DT1:   OFF. Measurements campaign is over and the setup is moved out (placed near the wall, Saleve side). Fe sources were been moved inside the safe.             

      EP-DT2 :  Detector installed in the EP-DT2 trolley. The aging test with eco-friendly gas mixture are going well and the recover from the EN-EL maintenance is on going.

      CMS-DT:  Expected to return to bunker later / next year. INFN still blocking activity outside Italy. 

      EcoGas :   New detector will be installed. After that the test campaign will be resumed using standard mixture (R134a, iso-butane, and SF6) 

      CMS-RPC :  Small trolley being prepared. 70x70cm. To be placed.
                             Radiation program resumed on trolley 1.

      ATLAS-RPC:    Coming back end of November. Trying to meet on site next week in order to check the position and the hardware installation.                        

      Cosmic (scintillators) Trolley :

      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe 

      UPSTREAM :          Default filter settings :  2.2
      DOWNSTREAM :   Default filter settings :  1

      --------------------------------------------------------------------------------------------------

       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
    • 09:40 → 09:45
      Long Term Planing - General Items 5m

      Current estimated NA beam start : 12/07/2021  (2.5 months delayed)

      ---------------------------------------------------------

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.

       
       
       
       
       
    • 09:45 → 09:50
      New requests for tests at GIF 5m

      introduction, goal of the test, plan, needs

      Bulgaria academy of science -> testing of new type of radiation monitor system

      A new setup of ALICE-RPC will come. More news in coming weeks.

      Lab on Fiber (LOF) dosimeter

      Gas recuperation system to be installed - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.
      (DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)

       
    • 09:50 → 09:55
      Infrastructure & Upgrades to the Facility 5m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      12 new gas lines installed and operational from today 29/10

      2 Chillers unit installed and in operation from yesterday 28/10. They have been installed in order to face the shutdown of the general cooling system of the entire EHN1

       
    • 09:55 → 10:00
      Announcements 5m
      • IMPACTS for 2020 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

      • New Announcements 5m
      • AOB 5m