LIU-SPS Machine Coordination Meeting 02/12/2020

Present: Andy Butterworth, Anthony Rey, Brennan Goddard, Chiara Pasquino, David Mcfarlane, Elena Shaposhnikova, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti, Frank Gerigk, Giulia Papotti ,Gregoire Hagmann , Hannes Bartosik , Ivan Karpov, James Ridewood ,Johan Dalla-Costa, Kevin Shing Bruce Li ,Lars Jensen, Luciana Kolbeck, Nico Madysa, Heiko Damerau, Philippe Baudrenghien, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain, Yannick Le Borgne. 

Matters arising and actions

  • VSC storage of some samples under vacuum not yet followed up; to be checked with team
  • High intensity scrubbing coating strategy for LS3; still open and needs to be folded into the schedule for 2023 --> Chiara will look into this
  • Can't have both long and short ion cycle in the SC, as too long, OP will look at longer term removal of this limit (SPS-OP)
  • Done: RF power interlocking implemented for Thales. Still to be clarified how this will be implemented for the Siemens and Philips plants. --> in progress
  • Blow-up status shown somehow in scraper application --> being looked at by Giulia and Eric
  • Send out request for logging checks to equipment groups (Kevin)
  • Inform about the use of the new logbook
  • New: Reyes to prepare shutdown lecture for "using optimisation tools in the control room"
  • New: Does RF need to have another discussion on margins and interlock thresholds for power/voltage requirements?
  • New: intermediate check point to be added for 2021 ion commissioning
  • New: supercycle preparation: June 2021: ion short test cycle past transition in. 

 

See AOB on RF interlocking below by Andy. 

News on dry-run and test progress

Kevin summarised the achievements with RFFG for the frequency program. The beam control is now configurable with functions e.g. frequency program, gammat etc. Not all tests could be carried out (e.g. radial steering) due to various issues with the LUMENS startup sequence manager causing various FESA processes for a given class to be alive at the same time. Heiko asked what the use case was for switching the sources of the LLRF frequency program . Kevin replied: simulated B-train during tests, B-train normal operation, frequency program directly from control room: MD and possible future operation. 

Dry run update - ALPS (Verena)

Verena summarised the outcome of the ALPS dry run from November 25, where also the new logbook as well as possible remote control configuration with x11vnc were tested. All BAs are now equipped with the latest ALPS FESA version. YASP is operational with all modes, except FIFO. FIFO and muliturn could not be tested during this dry run and will follow soon. The orbit and multi-orbit acquisition modes were thoroughly checked (a bug on the FESA class allocating data buffers after down-sampling was found and already fixed during the dry run). The extraction orbit interlock was tested first time. The interlocking functionality works well (confirmed on the BIS monitoring GUI). Several minor application issues were detected and will be followed up (BIS monitoring GUI as well as extraction orbit interlock GUI). The turn-by-turn interlock could not be fully verified due to issues in application software and FESA class. Work is still ongoing for that. Another dry run date before Christmas will be allocated.  

Ions commissioning schedule proposal (Philippe Baudrenghien) 

Philippe presented the detailed sequence of commissioning the RF system for ions and proposed a subset of this for the commissioning in 2021 fitting into the allocated three weeks in the schedule. The audience agreed with the proposal for 2021. In summary the proposal is reasonable, but will most certainly not allow to assess the full potential with LHC ions in the SPS. Verena and Kevin also remarked that while it is of importance to get experience with both stabilisation of the ion beams as well as slip stacking, priority should be given to fully test slip stacking with beam in case of conflict or shortage of time. Giulia mentioned that stability definitely needs to be addressed in 2021 to prepare sufficiently for 2022. Heiko added that some of the commissioning (stabilisation versus slip stacking) could be done in parallel or parasitically as different teams are involved. Reyes wanted to know whether the audience agreed with the proposal for 2022, where 5 weeks should be allocated to ion commissioning (4 weeks for LHC ions and 1 week for FT ions) according to Philippe. Verena replied that this request should be re-assessed at the end of 2021 after the first experience with ions in the SPS with the new LLRF. 

Plans for the SPS damper (Felix Armborst)

Postponed

Functions optimisation in generic GUI (Nico, Verena)

Nico presented a proposal for implementing generic optimisation of functions. The main idea is to exploit the existing incorporation implementation from LSA and only minimally extend the basic interface that users have to implement while preparing their optimisation problem. He also showed the status of the GUI and additional new features. Francesco remarked that it would be good to have tutorial for implementing and testing optimisation problems. Action: Reyes to prepare shutdown lecture for "using optimisation tools in the control room".  

BPT analysis: do we have all the plots?

Postponed

AOB

Andy presented the interlocking of the Siemens and Philips plants. The interlocking strategy will be the same as for the Thales plants with the exception of the fast interlock. OP will get information whether clipping occurred during the cycle to configure a fixed display or additional panel on the power application. Elena would like to clarify again the proposed interlock thresholds (i.e. for voltage clipping) to see whether they are consistent with the assumptions for the theoretical intensity reach. 

 