The ATLAS LVL1 system identifies the basic signatures of interesting physics with
high efficiency algorithms executed via custom electronics. It consists of three
components, the Calorimeter Trigger, the Muon Trigger and the Central Trigger. The
Central Trigger includes the Central Trigger Processor (CTP) and the
Muon-to-CTP-Interface (MUCTPI). The MUCTPI obtains muon candidate information from
the barrel and endcap muon trigger chambers, then produces muon multiplicities for
six configurable transverse momentum (pT) thresholds. The Calorimeter Trigger system
forms electron/photon, tau/hadron, and jet multiplicities as well as global event
energy information. Based on these local trigger objects the CTP makes the trigger
decision (L1A) with a configurable trigger menu. The L1A signal is distributed to all
subdetectors to initiate readout of the triggered event. The LVL1 latency is required
to be less than 2.5 us.
The ATLAS RoIB is a customized VME system. For each L1A it assembles a small amount
of information of the objects identified at LVL1 (RoI fragments) from the LVL1 system
into a full event record and passes it to the Level 2 Supervisors (L2SV). L2SVs
distribute the records to the Level 2 processing farm which runs the high level
trigger (HLT) algorithms. There event fragments are requested in fine granularity and
a decision to accept or reject is made. Events accepted by LVL2 are fully assembled
and formatted in the Event Builder (EB)'s destination nodes. Subsequently the complex
selection algorithms are executed on complete events on the EF farms.
Integration tests of the LVL1 system, the LVL2 system and the DAQ system have been
successfully performed by taking cosmic data with partial muon detector and
calorimeter. Cosmic data have been recorded in situ and analyzed. The results show
all subsystems function as expected and the full hardware and software chain
installed at the experiment site works in a coherent and consistent way.
Integration and commissioning of the trigger and DAQ system at the experiment site
are also being performed without the detector. Different tests have been done with
preselected simulated proton proton events through the trigger and dataflow chains.
The chain includes RoIB, LVL2, EB, EF and sometimes partial LVL1. The functionality
and the stability have been scrutinized. Some critical quantities for the final
system, such as the trigger rate and the event processing time, have been studied
using different trigger algorithms as well as different dataflow configurations.