Discussion I: Fabrication, Schedule, SM18 Testing & Integration
- Erk Jensen (CERN)
-
Dr Erk Jensen (CERN)14/12/2012, 10:40Outline of the crab cavity work package within the HL-LHC upgrade including thedistribution of R&D tasks, time line for R&D and construction, cost estimate over the duration of the project, and man power estimates.Go to contribution page
-
Ofelia Capatina (CERN)14/12/2012, 11:10Fabrication of the different types of Helium vessels and tuner systems, their advantage and disadvantages should be reviewed. Challenges in the design choice and fabrication steps along with feasibility of a two cavity cryostat within the specified scheduled should be reviewed and mitigation should be discussed.Go to contribution page
-
Tommy Peterson (Fermilab)14/12/2012, 11:40Fabrication of the different types of cryostat and their advantage and disadvantages should be reviewed. Challenges in the design choice, fabrication steps, integration along with feasibility of a two cavity cryostat within the specified scheduled should be reviewed and mitigation should be discussed.Go to contribution page
-
14/12/2012, 12:10