Over the last couple of years, The Genome Center at Washington University in St. Louis has been involved with the planning and construction of a new data center. We will provide updates since our data center presentation at HEPiX Fall 2007 in St. Louis. In addition, we will share our experiences and lessons learned as we prepare to move into the new data center in May 2008.

Primary author

Gary Stiehr (The Genome Center at Washington University)