GIF++ installation and schedule meeting
-
-
09:00
→
09:20
Summary/feedback from last test beam 20mSpeakers: Barbara Alvarez Gonzalez (CERN), Giulio Aielli (Universita e INFN Roma Tor Vergata (IT)), Katerina Kuznetsova (Petersburg Nuclear Physics Institut (RU)), Nicolas Zaganidis (Ghent University (BE))
-
09:20
→
09:40
Plan for next wednesday (MD) / thursday (source scan) 20m
ATL-CSC need two short access (30 min each):
1st before Friday
2nd (about) Monday
wed 31/8
ATL-MDT need to open the bunker.
ATL-MM need false floor to be open.
Roberto to request opening bunker and false floor.
CMS-DT will enter on September 7 or August 31? Roberto check with Ignacio.
CMS-CSC vs ATL-RPC vs ATL-TGC vs ATL-MM
CMS-CSC will move out for a couple of days not to be in front of RPC (to be re-discussed)
Downstream area setups:
-1st : discussion about position and size (9 am)
-2nd : beginning next week
-3rd : onsite next Wednesday
CMS-DT and Roberto will check next Wednesday (9am) if it is possible to remove temporarily the rail after the CMS-DT beam period (leaving the rail in the bunker if it is not a problem for other users)
Thu 1/9
plan according to test beam.
-
09:45
→
10:05
Preparation of next test beam periods 20m
updated version of setups position and schedule for next test beam.
Speaker: Roberto Guida (CERN) - 10:05 → 10:20
-
10:20
→
10:40
Scintillator beam trigger 20mSpeaker: Antonio Bianchi (Universita e INFN Torino (IT))
-
10:40
→
11:00
ATL-CSC 20m
introduction, goal of the test, plan, needs
Speaker: Paris Moschovakos (National Technical Univ. of Athens (GR)) -
11:00
→
11:05
Run coordinator 5mSpeaker: Antonio Bianchi (Universita e INFN Torino (IT))
-
09:00
→
09:20