Conveners
C2OrD - Large Scale Refrigeration and Liquefaction III
- Laurent Tavian (CERN)
- Brian DeGraff (ORNL)
-
Sergiy Putselyk11/07/2017, 15:00Invited Oral Presentation
In order to cover the required cryogenic load, several cryogenic groups, e.g. at CERN, ITER, JLab, SLAC, have to install several refrigerators with maximal power capacities each. As an alternative, development of larger refrigerators up to 120kW power could be an alternative to the installation of several “small” ones. In the present paper, the novel concept of 60÷120 kW refrigerator is...
Go to contribution page -
Mr Laurent Tavian (CERN)11/07/2017, 15:30Contributed Oral Presentation
Following the update of the European strategy in particle physics, CERN has undertaken an international study of possible future circular colliders beyond the LHC. The study considers several options for very high-energy hadron-hadron, electron-positron and hadron-electron colliders. From the cryogenics point of view, the most challenging option is the hadron-hadron collider (FCC-hh) for which...
Go to contribution page -
Mr Laurent Delprat (CERN)11/07/2017, 15:45Contributed Oral Presentation
After the successful Run 1 (2010-2012), the LHC entered its first Long Shutdown period (LS1, 2013-2014). During LS1 the LHC cryogenic system went under a complete maintenance and consolidation program. The LHC resumed operation in 2015 with an increased beam energy from 4 TeV to 6.5 TeV. Prior to the new physics Run 2 (2015-2018), the LHC was progressively cooled down from ambient to the 1.9 K...
Go to contribution page -
Daniel Alexander Berkowitz Zamora (CERN)11/07/2017, 16:00Contributed Oral Presentation
The cryogenic system of the LHC will be upgraded by 2025 to comply with a considerable increase of beam induced heat loads deriving from higher beam currents and peak luminosity levels from the High-Luminosity LHC. The current baseline foresees a modified sectorization scheme with three additional cryogenic plants dedicated to cool the insertions at LHC’s points 1, 4 and 5, reducing the...
Go to contribution page -
Dr Bernd Petersen (DESY)11/07/2017, 16:15Contributed Oral Presentation
Commissioning the XFEL cryogenic system has begun in the middle of 2015 by putting into operation components necessary for operating the XFEL injector. The injector was cooled down to 2K at the end of 2015 and operated - including beam commissioning - until August 2016. After warming up of the whole XFEL cryogenic system, commissioning remaining components including the 1.5 km long...
Go to contribution page -
Dr Tobias Schnautz (DESY)11/07/2017, 16:30Contributed Oral Presentation
The RF operation of the about 800 superconducting 1.3GHz 9-cell cavities of the XFEL linac requires helium II bath cooling at 2K, corresponding to a vapor pressure of 3100 Pa. After the first cool-down of the XFEL linac to 4K in December, 27th,2016 the operation of the 2K cryogenic system was started in January, 2th 2017. The 2K cryogenic system consist of a 4-stage set of cold compressors to...
Go to contribution page