uTCA (Tom)
- Go/no-go for BE/CO support by the end of 2017 (RF PoC will determine)
- If Go then operational platform in parallel to VME by 2021
- BI to identify whether uTCA option for new systems / upgrades
- mTCA conference at DESY by end of 2017 (http://mtcaws.desy.de/) - send people from BI?
- VME support expected for another 15 years
MEN-A25 (Adam)
- DMA (zero-copy) access not yet available from MEN (expected in the coming weeks)
- First test systems to equipment groups by Nov'17
- First operational systems expected by Q1/2018
- 2nd Ethernet port can be made with XMC mezzanine (quote pending at BE/CO)
LIU-BWS prototypes (Jose)
- PSB scanner: issue with glass disk slippage will be resolved next week
- SPS scanner: use system for HDR detection (bunch by bunch)
- Calibration bench: compensation of systematic errors into operational installation to be verified (noise/vibration)
- Milestone for metal disk yet to be decided (Ray et al)
AWAKE (Stefano)
- Next phase - installation to be finished by end of October (supports for spectrometer line)
- Simulaneous OTR measurements (p+, e- and laser) being assessed
- Influence of plasma on downstream BPM (button/stripline) still needs more studies
- Budget requested for short bunch lenght measurements for 2018 (CLEAR)