Manufacturing strategy for the RFD cavity, copper trials and present status of the Nb cavities
Issues encountered during the manufacturing and impact on schedule
Technology transfer to partner collaborations and industry
Industrial production of the pre-series DQW cavities with RI
Present status including the re-scoping and changes implemented during the first phase of the contract
Status of the documentation, qualifications, readiness for fabrication and CERN acceptance tests
Impact on the schedule
US-AUP strategy for RFD-DC including scope, RF geometry, treatment, testing planning for prototypes and series cavities
Compliance with engineering specifications and safety requirements including fabrication, documentation, qualification status, issues
Reliability of the existing setups and acceptance criteria agreements with CERN
Experience industrial partner and next key milestones
FPCs, HOM couplers and field antenna design and prototyping
Issues encountered during the SPS phase and mitigation measures including transport considerations
Strategy for RFD and DQW (including RF feedthroughs) both at CERN and Canada/UK
Status of fabrication/doc/qualification/documentation