Laurent Jean Tavian (CERN)12/03/2020, 11:10
o Assumption to maintain for all WPs the current baseline planning (keeping delay entirely as contingency) and assess eventual storage needs and cost consequences in 2024;
Go to contribution page
o Resources management by end of the HL-LHC Project (FSUs, MPA, Staff). -
Benoit Delille (CERN), Isabelle Laugier (CERN)12/03/2020, 11:35
o Can some of the high-risk items be retired by re-arranging the production?
Go to contribution page
o Opportunities and consequences of re-profiling of the spending profile.
o Possible gains in MPA due to replacement by staff in 2024?