Conveners
Session 1 - Surveying and Alignment I: Session 1 - Surveying and Alignment I
- Helene Mainaud Durand (CERN)
The LCLS-II (Linac Coherent Light Source II) project is an upgrade to the world’s first hard X-ray free-electron laser moving from 120 pulses per second to 1 million pulses per second. The LCLSII project includes a new 700 m long superconducting Linac, 3 km of beam transport lines, a new beam switch area to switch between the superconducting beam source and the Cu beam source, 2 new undulators...
The Advanced Photon Source (APS) is a third generation synchrotron X-ray facility located at Argonne National Laboratory that has been in operation since 1996. Over the next few years, the APS will undergo an extensive upgrade that will replace the current electron storage ring with a new, state-of-the-art machine. The upgraded APS will generate X-rays up to 500 times brighter than those...