Review on PSB 160 MeV H- Injection

Europe/Zurich
30/7-018 - Kjell Johnsen Auditorium (CERN)

30/7-018 - Kjell Johnsen Auditorium

CERN

Meyrin Site Building 30 7th Floor Room 18
190
Show room on map
PLUM Michael A (Oak Ridge National Laboratory)
Description
CERN is currently designing a new H- charge-exchange injection system for the PSB, to inject the 160 MeV H- beam from the new LINAC4. The purpose of this review is to validate the engineering design of the injection equipment, to eliminate all outstanding questions, and to examine the feasibility of the proposed injection system commissioning strategy and its timeline.
- 160 MeV H- Injection into the CERN PSB
- Dump and Current Measurement of Unstripped H`ions at the Injection from the Cern LINAC4 Into the PS Booster
- Lattice issues of the PS with H- charge exchange injection hardware
- Layout considerations for the PSB H- injection system
- Linac4 Technical Design Report
- Operational considerations for the PSB H- injection system
- Stripping foil issues for H- injection into PSB at 160 MeV
- Stripping foils for the PSB H- injection system
  • Wednesday 9 November
    • 1
      Welcome and Introduction to LIU Project 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      CERN has recently built the Large Hadron Collider (LHC), a superconducting circular particle accelerator designed for colliding two proton beams at 7 TeV energy. In order for the LHC to achieve ultimate beam parameters, CERN has launched a long-term program for the progressive replacement or upgrade of the old chain of accelerators presently used as injectors for the LHC, the so-called LHC Injectors Upgrade (LIU) project, and Linac4 is the first element of this program. Linac4 is a linear accelerator for negative hydrogen ions, which will replace the old Linac2 as linear injector for the CERN PS Booster. The 160 MeV H- beam from Linac4 will be injected into the 4 superimposed rings of the PS Booster by means of charge-exchange injection using, for each PSB ring, a set of 4 pulsed dipole magnets creating the required injection bump. A carbon stripping foil in the injection region will convert the H- beam to H+. The presentation gives an introduction to the plans for the upgrade of the PS Booster within the LIU project with focus on the modification of the injection region.
      Speaker: Dr Klaus Hanke (CERN)
    • 2
      PSB H- Injection Concept 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      Speaker: Dr Brennan Goddard (CERN)
      Slides
    • 3
      Painting, injection matching, emittances and beam dynamics 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      An overview on the new PSB H- injection system is presented in this talk. The principle of longitudinal painting, consisting in energy modulation from Linac4, is introduced. Transverse painting in the horizontal plane, by means of four existing PSB kicker magnets (KSW), is described. Results of extensive and detailed beam dynamic studies allowed to precisely define the KSW generators waveforms fulfilling the requirements in intensities and emittances of all the PSB users. Preliminary studies have been carried out to evaluate how to obtain the required vertical emittance and the option of a transverse painting, also in the vertical plane, is explored.
      Speaker: Dr Chiara Bracco (CERN)
      Transparents
    • 4
      BSW Chicane Magnets 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      Per PS Booster ring, 4 outside vacuum magnets will be installed to provide the injection bump through the stripping foil. The first magnet is a septum and the following magnets are window frame dipoles, of which the last has to cope with the unstripped particle beam dumps. The talk will describe the constraints imposed on these injection chicane magnets and present the baseline implementation.
      Speaker: Mr Jan Borburgh (CERN)
      Slides
    • 10:30
      Coffee Break 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
    • 5
      KSW Painting magnets 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      Speaker: Luis Miguel Coralejo Feliciano (CERN)
      Slides
    • 6
      Internal H0/- Dump 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      The conceptual ideas for the dumping of the unstripped H0 and H- ions coming from the PSB injection region at the energy and beam parameters due to the Linac4 future connection is presented in this talk. The dump core itself covers longitudinally the second half of the BSW4 chicane magnet, close by but out of the trajectory of the circulating H+ beam. Due to dimension constraints and the heat load to the core, the dump has to be actively cooled via the back-flange possibly without any feed-through, which impose the need to guarantee the good holding of the core together with the good thermal contact between the flange and the core itself. Specifications, parameters, layout and constraint are presented. First results based on studies on activation as well as thermo-mechanical behaviour are also presented and discussed. Finally standing questions and issues are addressed.
      Speaker: Cesare Maglioni (CERN)
    • 7
      Injection foils and handling system 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      The linac4 beam will be injected horizontally into the PSB by means of an H- charge-exchange injection system using a graphite stripping foil to paint the beam into the required emittance. This presentation will describes the hardware requirements and constraints, the performance specifications of the stripping foil and the conceptual design of the foil exchange unit and motorisation.
      Speaker: Wim Weterings (CERN)
      Slides
    • 8
      PSB H- Injection Vacuum analysis 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      The Vacuum analysis for the PSB H- injection has been done by means of the electrical network – vacuum analogy: through this method it’s possible to design complex vacuum line, taking into account the gas loads, the conductances, the pumping speeds applied and the target pressure to reach. This presentation shows how the main gas sources have been taken into account (water degassing from inner surfaces, thermal degassing from the dump, ion induced desorption, beam losses, etc.) in order to define the issues to reach the target pressure of 5e-9 mbar.
      Speaker: Mrs Chiara Pasquino (CERN)
      Slides
    • 12:15
      Lunch Break Restaurant 2 NOVAE / 504

      Restaurant 2 NOVAE / 504

      CERN

    • 9
      Beam Instrumentation in the BOOSTER injection region 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      Beam instrumentation is essential for the commissioning phase of the PSB injection zone with the Linac4 beam, and for routine operation later on. The following observables are requested for that purpose: Beam profiles for steering and injection matching. The stripping efficiency is also monitored downstream the foil, in addition to the visual inspection of the foil. A fast machine protection system coupled with beam loss monitors is needed too. In this talk, analysis and solutions based on specifications issued by the machine physicists are proposed by the Beam Instrumentation Group. This very preliminary phase arouse a set of questions which needs deeper investigations.
      Speaker: Jocelyn Tan (CERN)
      Transparents
    • 10
      Beam losses 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      Speaker: Christian Carli (CERN)
      Slides
    • 11
      Commissioning strategy and timeline 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
      The novel H- injection of Linac4 into the PS Booster will require a complete rebuilding of the PSB injection section. The connection is presently foreseen to be ready for late 2015. 3 months must be available for installation of the new injection equipment and related machine modifications after one month of radiation cool-down, followed by 3 months of beam commissioning. The presentation will mention the dry run tests that will close up the installation phase and will define the starting conditions for beam commissioning. This has been divided up in 4 distinct phases; for each of these phases the required starting conditions will be mentioned and planned measurements and adjustments described in detail.
      Speaker: Dr Bettina Mikulec (CERN)
      Slides
    • 15:30
      Coffee Break 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
    • 12
      Questions by Reviewers, and discussions with experts 30/7-018 - Kjell Johnsen Auditorium

      30/7-018 - Kjell Johnsen Auditorium

      CERN

      Meyrin Site Building 30 7th Floor Room 18
      190
      Show room on map
  • Thursday 10 November