Major installation advancements at AD -> Magnet is now cooling down, it is planned to take Antiprotons in March when AD is back and running again
ECR for RC7 (PUMA at ISOLDE experimental area) now ready to be shared in engineering check
PUMA installation planning at ISOLDE: transport planned with Antiprotons or electrons planned for second half of the year, RC7 will start construction at ISOLDE in Spring to anticipate transport later in the year
Transport still needs production of load spreader -> needs to be announced at least 3 months in advance; needs also preparing the Diesel generators and renting of the special truck
Concerns by VSC: only time for support until July (start of LS3), afterwards will be very tight on ressources
Mark will send Vincent the final RC7 layout to be integrated
10:25
→
10:40
WP6: BEAM optics and elements; AOBs15m37/R-022 - 37/R-022
Birst DB box failed vacuum acceptance test, will have to be cleaned again
Some delay for one of the drift tubes that needs NEG coating: can also operate for now without coating which could be done later
VSC installation should be done before beginning of July when the LS3 starts
Very first part (first quadrupole until valve) could be installed anytime; bottlenecks for downstream parts are the installation of the beam telescopes and the first BI box